प्रश्न
Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:
| Job | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 30 | 37 | 40 | 28 | 40 |
| 2 | 40 | 24 | 27 | 21 | 36 |
| 3 | 40 | 32 | 33 | 30 | 35 |
| 4 | 25 | 38 | 40 | 36 | 36 |
| 5 | 29 | 62 | 41 | 34 | 39 |
Find the optimal assignment schedule.
Advertisements
उत्तर
Step 1:
Since it is a maximization problem, subtract each of the elements in the table from the largest element, i.e., 62
| Jobs | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 32 | 25 | 22 | 34 | 22 |
| 2 | 22 | 38 | 35 | 41 | 26 |
| 3 | 22 | 30 | 29 | 32 | 27 |
| 4 | 37 | 24 | 22 | 26 | 26 |
| 5 | 33 | 0 | 21 | 28 | 23 |
Step 2:
Row minimum Subtract the smallest element in each row from every element in its row.
The matrix obtained is given below:
| Jobs | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 10 | 3 | 0 | 12 | 0 |
| 2 | 0 | 16 | 13 | 19 | 4 |
| 3 | 0 | 8 | 7 | 10 | 5 |
| 4 | 15 | 2 | 0 | 4 | 4 |
| 5 | 33 | 0 | 21 | 28 | 23 |
Step 3:
Column minimum Subtract the smallest element in each column of assignment matrix obtained in step 2 from every element in its column.
| Jobs | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 10 | 3 | 0 | 8 | 0 |
| 2 | 0 | 16 | 13 | 15 | 4 |
| 3 | 0 | 8 | 7 | 6 | 5 |
| 4 | 15 | 2 | 0 | 0 | 4 |
| 5 | 33 | 0 | 21 | 24 | 23 |
Step 4:
Draw minimum number of vertical and horizontal lines to cover all zeros.
First cover all rows and columns which have maximum number of zeros.
| Jobs | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 10 | 3 | 0 | 8 | 0 |
| 2 | 0 | 16 | 13 | 15 | 4 |
| 3 | 0 | 8 | 7 | 6 | 5 |
| 4 | 15 | 2 | 0 | 0 | 4 |
| 5 | 33 | 0 | 21 | 24 | 23 |
Step 5:
From step 4, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e., 5.
∴ Select smallest element from all the uncovered elements, i.e., 4 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
| Jobs | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 14 | 3 | 0 | 8 | 0 |
| 2 | 0 | 12 | 9 | 11 | 0 |
| 3 | 0 | 4 | 3 | 2 | 1 |
| 4 | 19 | 2 | 0 | 0 | 4 |
| 5 | 37 | 0 | 21 | 24 | 23 |
Step 6:
Draw minimum number of vertical and horizontal lines to cover all zeros.
| Jobs | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 14 | 3 | 0 | 8 | 0 |
| 2 | 0 | 12 | 9 | 11 | 0 |
| 3 | 0 | 4 | 3 | 2 | 1 |
| 4 | 19 | 2 | 0 | 0 | 4 |
| 5 | 37 | 0 | 21 | 24 | 23 |
Step 7:
From step 6, minimum number of lines covering all the zeros are 5, which is equal to order of the matrix, i.e., 5.
∴ Select a row with exactly one zero, enclose that zero in () and cross out all zeros in its respective column.
Similarly, examine each row and column and mark the assignment ().
∴ The matrix obtained is as follows:
| Jobs | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 14 | 3 | 0 | 8 | 0 |
| 2 | 0 | 12 | 9 | 11 | 0 |
| 3 | 0 | 4 | 3 | 2 | 1 |
| 4 | 19 | 2 | 0 | 0 | 4 |
| 5 | 37 | 0 | 21 | 24 | 23 |
Step 8:
The matrix obtained in step 7 contains exactly one assignment for each row and column.
∴ Optimal assignment schedule is as follows:
| Jobs | Machines | Profit (in ₹) |
| 1 | C | 40 |
| 2 | E | 36 |
| 3 | A | 40 |
| 4 | D | 36 |
| 5 | B | 62 |
∴ Total maximum profit = 40 + 36 + 40 + 36 + 62 = ₹ 214.
APPEARS IN
संबंधित प्रश्न
Solve the following minimal assignment problem and hence find the minimum value :
| I | II | III | IV | |
| A | 2 | 10 | 9 | 7 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
Service Time ( in hrs.)
| Counters | Salesmen | |||
| A | B | C | D | |
| W | 41 | 72 | 39 | 52 |
| X | 22 | 29 | 49 | 65 |
| Y | 27 | 39 | 60 | 51 |
| Z | 45 | 50 | 48 | 52 |
Solve the following minimal assignment problem :
| Machines | A | B | C | D | E |
| M1 | 27 | 18 | ∞ | 20 | 21 |
| M2 | 31 | 24 | 21 | 12 | 17 |
| M3 | 20 | 17 | 20 | ∞ | 16 |
| M4 | 21 | 28 | 20 | 16 | 27 |
Solve the following minimal assignment problem and hence find minimum time where '- ' indicates that job cannot be assigned to the machine :
| Machines | Processing time in hours | ||||
| A | B | C | D | E | |
| M1 | 9 | 11 | 15 | 10 | 11 |
| M2 | 12 | 9 | - | 10 | 9 |
| M3 | - | 11 | 14 | 11 | 7 |
| M4 | 14 | 8 | 12 | 7 | 8 |
Solve the following maximal assignment problem :
| Branch Manager | Monthly Business ( Rs. lakh) | |||
| A | B | C | D | |
| P | 11 | 11 | 9 | 9 |
| Q | 13 | 16 | 11 | 10 |
| R | 12 | 17 | 13 | 8 |
| S | 16 | 14 | 16 | 12 |
In a factory there are six jobs to be performed each of which should go through two machines A and B in the order A - B. The processing timing (in hours) for the jobs arc given here. You are required to determine the sequence for performing the jobs that would minimize the total elapsed time T. What is the value of T? Also find the idle time for machines · A and B.
| Jobs | J1 | J2 | J3 | J4 | J5 | J6 |
| Machine A | 1 | 3 | 8 | 5 | 6 | 3 |
| MAchine B | 5 | 6 | 3 | 2 | 2 | 10 |
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:
| Jobs | Machines (Processing Cost in ₹) |
|||
| P | Q | R | S | |
| A | 31 | 25 | 33 | 29 |
| B | 25 | 24 | 23 | 21 |
| C | 19 | 21 | 23 | 24 |
| D | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
The assignment problem is said to be unbalance if ______
The assignment problem is said to be balanced if ______.
The objective of an assignment problem is to assign ______.
Fill in the blank :
An _______ is a special type of linear programming problem.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
Solve the following problem :
A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.
| I | II | III | IV | |
| A | 7 | 25 | 26 | 10 |
| B | 12 | 27 | 3 | 25 |
| C | 37 | 18 | 17 | 14 |
| D | 18 | 25 | 23 | 9 |
How should the tasks be allocated, one to a man, as to minimize the total man hours?
Choose the correct alternative:
The assignment problem is generally defined as a problem of ______
Choose the correct alternative:
When an assignment problem has more than one solution, then it is ______
State whether the following statement is True or False:
The objective of an assignment problem is to assign number of jobs to equal number of persons at maximum cost
State whether the following statement is True or False:
In assignment problem, if number of columns is greater than number of rows, then a dummy row is added
State whether the following statement is True or False:
In assignment problem each worker or machine is assigned only one job
What is the Assignment problem?
What is the difference between Assignment Problem and Transportation Problem?
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 120 | 100 | 80 |
| 2 | 80 | 90 | 110 | |
| 3 | 110 | 140 | 120 | |
Assign the programmers to the programme in such a way that the total computer time is least.
Choose the correct alternative:
North – West Corner refers to ______
Choose the correct alternative:
If number of sources is not equal to number of destinations, the assignment problem is called ______
A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:
| To | |||||||
| 7 | 8 | 9 | 10 | 11 | 12 | ||
| From | 1 | 31 | 62 | 29 | 42 | 15 | 41 |
| 2 | 12 | 19 | 39 | 55 | 71 | 40 | |
| 3 | 17 | 29 | 50 | 41 | 22 | 22 | |
| 4 | 35 | 40 | 38 | 42 | 27 | 33 | |
| 5 | 19 | 30 | 29 | 16 | 20 | 33 | |
| 6 | 72 | 30 | 30 | 50 | 41 | 20 | |
How should the truck be dispersed so as to minimize the total distance travelled?
A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
| I | II | III | IV | V | |
| A | 150 | 120 | 175 | 180 | 200 |
| B | 125 | 110 | 120 | 150 | 165 |
| C | 130 | 100 | 145 | 160 | 170 |
| D | 40 | 40 | 70 | 70 | 100 |
| E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 31 | 25 | 33 | 29 |
| Q | 25 | 24 | 23 | 21 |
| R | 19 | 21 | 23 | 24 |
| S | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
A department store has four workers to pack goods. The times (in minutes) required for each worker to complete the packings per item sold is given below. How should the manager of the store assign the jobs to the workers, so as to minimize the total time of packing?
| Workers | Packing of | |||
| Books | Toys | Crockery | Cutlery | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 12 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 7 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |