Choose the correct alternative: The purpose of a dummy row or column in an assignment problem is to

Advertisements
Advertisements

प्रश्न

Choose the correct alternative:

The purpose of a dummy row or column in an assignment problem is to

विकल्प

  • prevent a solution from becoming degenerate

  • balance between total activities and total resources

  • provide a means of representing a dummy problem

  • none of the above

MCQ
Advertisements

उत्तर

balance between total activities and total resources

shaalaa.com
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Exercise 10.4 [पृष्ठ २६१]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 12 TN Board
अध्याय 10 Operations Research
Exercise 10.4 | Q 10 | पृष्ठ २६१

संबंधित प्रश्न

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:

         Jobs

 

 

                          Machines

P

Q

R

S

                Processing Cost (Rs.)

 

A

31

25

33

29

B

25

24

23

21

C

19

21

23

24

D

38

36

34

40

 How should the jobs be assigned to the four machines so that the total processing cost is minimum?


Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
                                             Service Time ( in hrs.)

Counters Salesmen
A B C D
W 41 72 39 52
X 22 29 49 65
Y 27 39 60 51
Z 45 50 48 52

Solve the following maximal assignment problem :

Branch Manager Monthly Business ( Rs. lakh)
A B C D
P 11 11 9 9
Q 13 16 11 10
R 12 17 13 8
S 16 14 16 12

 


Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:

Job Machines (Profit in ₹)
A B C D E
1 30 37 40 28 40
2 40 24 27 21 36
3 40 32 33 30 35
4 25 38 40 36 36
5 29 62 41 34 39

Find the optimal assignment schedule.


The objective of an assignment problem is to assign ______. 


Fill in the blank :

An _______ is a special type of linear programming problem.


Solve the following problem :

A dairy plant has five milk tankers, I, II, III, IV and V. These milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.

  I II III IV V
A 150 120 175 180 200
B 125 110 120 150 165
C 130 100 145 160 175
D 40 40 70 70 100
E 45 25 60 70 95

How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?


If the given matrix is ______ matrix, the assignment problem is called balanced problem


What is the Assignment problem?


A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.

  Programmers
    P Q R
Programmers 1 120 100 80
  2 80 90 110
  3 110 140 120

Assign the programmers to the programme in such a way that the total computer time is least.