Choose the correct alternative:
The assignment problem is generally defined as a problem of ______
विकल्प
maximization
minimization
allocation
restriction
Advertisements
उत्तर
allocation
APPEARS IN
संबंधित प्रश्न
Solve the following minimal assignment problem :
| Machines | A | B | C | D | E |
| M1 | 27 | 18 | ∞ | 20 | 21 |
| M2 | 31 | 24 | 21 | 12 | 17 |
| M3 | 20 | 17 | 20 | ∞ | 16 |
| M4 | 21 | 28 | 20 | 16 | 27 |
Determine `l_92 and l_93, "given that" l_91 = 97, d_91 = 38 and q_92 = 27/59`
Solve the following minimal assignment problem and hence find minimum time where '- ' indicates that job cannot be assigned to the machine :
| Machines | Processing time in hours | ||||
| A | B | C | D | E | |
| M1 | 9 | 11 | 15 | 10 | 11 |
| M2 | 12 | 9 | - | 10 | 9 |
| M3 | - | 11 | 14 | 11 | 7 |
| M4 | 14 | 8 | 12 | 7 | 8 |
Solve the following maximal assignment problem :
| Branch Manager | Monthly Business ( Rs. lakh) | |||
| A | B | C | D | |
| P | 11 | 11 | 9 | 9 |
| Q | 13 | 16 | 11 | 10 |
| R | 12 | 17 | 13 | 8 |
| S | 16 | 14 | 16 | 12 |
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:
| Jobs | Machines (Processing Cost in ₹) |
|||
| P | Q | R | S | |
| A | 31 | 25 | 33 | 29 |
| B | 25 | 24 | 23 | 21 |
| C | 19 | 21 | 23 | 24 |
| D | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
The objective of an assignment problem is to assign ______.
Fill in the blank :
When an assignment problem has more than one solution, then it is _______ optimal solution.
Fill in the blank :
An _______ is a special type of linear programming problem.
State whether the following is True or False :
In assignment problem, each facility is capable of performing each task.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
Solve the following problem :
A dairy plant has five milk tankers, I, II, III, IV and V. These milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
| I | II | III | IV | V | |
| A | 150 | 120 | 175 | 180 | 200 |
| B | 125 | 110 | 120 | 150 | 165 |
| C | 130 | 100 | 145 | 160 | 175 |
| D | 40 | 40 | 70 | 70 | 100 |
| E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
Choose the correct alternative:
When an assignment problem has more than one solution, then it is ______
Choose the correct alternative:
The assignment problem is said to be balanced if ______
State whether the following statement is True or False:
In assignment problem, if number of columns is greater than number of rows, then a dummy row is added
State whether the following statement is True or False:
In assignment problem each worker or machine is assigned only one job
What is the Assignment problem?
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 120 | 100 | 80 |
| 2 | 80 | 90 | 110 | |
| 3 | 110 | 140 | 120 | |
Assign the programmers to the programme in such a way that the total computer time is least.
Choose the correct alternative:
North – West Corner refers to ______
Choose the correct alternative:
If number of sources is not equal to number of destinations, the assignment problem is called ______
Choose the correct alternative:
The purpose of a dummy row or column in an assignment problem is to
Choose the correct alternative:
The solution for an assignment problem is optimal if
A car hire company has one car at each of five depots a, b, c, d and e. A customer in each of the fine towers A, B, C, D and E requires a car. The distance (in miles) between the depots (origins) and the towers(destinations) where the customers are given in the following distance matrix.
| a | b | c | d | e | |
| A | 160 | 130 | 175 | 190 | 200 |
| B | 135 | 120 | 130 | 160 | 175 |
| C | 140 | 110 | 155 | 170 | 185 |
| D | 50 | 50 | 80 | 80 | 110 |
| E | 55 | 35 | 70 | 80 | 105 |
How should the cars be assigned to the customers so as to minimize the distance travelled?
A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:
| To | |||||||
| 7 | 8 | 9 | 10 | 11 | 12 | ||
| From | 1 | 31 | 62 | 29 | 42 | 15 | 41 |
| 2 | 12 | 19 | 39 | 55 | 71 | 40 | |
| 3 | 17 | 29 | 50 | 41 | 22 | 22 | |
| 4 | 35 | 40 | 38 | 42 | 27 | 33 | |
| 5 | 19 | 30 | 29 | 16 | 20 | 33 | |
| 6 | 72 | 30 | 30 | 50 | 41 | 20 | |
How should the truck be dispersed so as to minimize the total distance travelled?
A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 31 | 25 | 33 | 29 |
| Q | 25 | 24 | 23 | 21 |
| R | 19 | 21 | 23 | 24 |
| S | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
A job production unit has four jobs P, Q, R, S which can be manufactured on each of the four machines I, II, III and IV. The processing cost of each job for each machine is given in the following table :
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 31 | 25 | 33 | 29 |
| Q | 25 | 24 | 23 | 21 |
| R | 19 | 21 | 23 | 24 |
| S | 38 | 36 | 34 | 40 |
Complete the following activity to find the optimal assignment to minimize the total processing cost.
Solution:
Step 1: Subtract the smallest element in each row from every element of it. New assignment matrix is obtained as follows :
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 6 | 0 | 8 | 4 |
| Q | 4 | 3 | 2 | 0 |
| R | 0 | 2 | 4 | 5 |
| S | 4 | 2 | 0 | 6 |
Step 2: Subtract the smallest element in each column from every element of it. New assignment matrix is obtained as above, because each column in it contains one zero.
Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros:
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 6 | 0 | 8 | 4 |
| Q | 4 | 3 | 2 | 0 |
| R | 0 | 2 | 4 | 5 |
| S | 4 | 2 | 0 | 6 |
Step 4: From step 3, as the minimum number of straight lines required to cover all zeros in the assignment matrix equals the number of rows/columns. Optimal solution has reached.
Examine the rows one by one starting with the first row with exactly one zero is found. Mark the zero by enclosing it in (`square`), indicating assignment of the job. Cross all the zeros in the same column. This step is shown in the following table :
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 6 | 0 | 8 | 4 |
| Q | 4 | 3 | 2 | 0 |
| R | 0 | 2 | 4 | 5 |
| S | 4 | 2 | 0 | 6 |
Step 5: It is observed that all the zeros are assigned and each row and each column contains exactly one assignment. Hence, the optimal (minimum) assignment schedule is :
| Job | Machine | Min.cost |
| P | II | `square` |
| Q | `square` | 21 |
| R | I | `square` |
| S | III | 34 |
Hence, total (minimum) processing cost = 25 + 21 + 19 + 34 = ₹`square`