Advertisements
Advertisements
प्रश्न
A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 8 | 26 | 17 | 11 |
| Q | 13 | 28 | 4 | 26 | |
| R | 38 | 19 | 18 | 15 | |
| S | 9 | 26 | 24 | 10 | |
How should the tasks be allocated to subordinates so as to minimize the total manhours?
Advertisements
उत्तर
Here the number of rows and columns are equal.
∴ The given assignment problem is balanced.
Step 1: Select the smallest element in each row and subtract this from all the elements in its row.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 18 | 9 | 3 |
| Q | 9 | 24 | 0 | 22 | |
| R | 23 | 4 | 3 | 0 | |
| S | 0 | 17 | 15 | 1 | |
Step 2: Select the smallest element in each column and subtract this from all the elements in its column.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 9 | 20 | 0 | 22 | |
| R | 23 | 0 | 3 | 0 | |
| S | 0 | 13 | 15 | 1 | |
Step 3: (Assignment)
Examine the rows with exactly one zero Mark the zero by □. Mark other zeros in its row by X.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 9 | 20 | 0 | 22 | |
| R | 23 | 0 | 3 | 0 | |
| S | 0 | 13 | 15 | 1 | |
Step 4: Now examine the columns with exactly one zero. Mark the zero by □. Mark other zeros in its row by X.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 9 | 20 | 0 | 22 | |
| R | 23 | 0 | 3 | 0 | |
| S | 0 | 13 | 15 | 1 | |
Step 5: Cover all the zeros of table 4 with three lines, since three assignments were made check (✓) row S since it has no assignment.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 9 | 20 | 0 | 22 | |
| R | 23 | 0 | 3 | 0 | |
| ✓ | S | 0 | 13 | 15 | 1 |
Step 6: Develop the new revised tableau. Examine those elements that are not covered by a line in table 5.
Take the smallest element.
This is 1 (one) our case.
By subtracting 1 from the uncovered cells.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 10 | 20 | 0 | 22 | |
| R | 24 | 0 | 3 | 0 | |
| S | 0 | 12 | 14 | 0 | |
[Adding 1 to elements (Q, S, R) that line at the intersection of two lines]
Step 7: Go to step 3 and repeat the procedure until you arrive at an optimal assignment.
Step 8: Determine an assignment.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 10 | 20 | 0 | 22 | |
| R | 24 | 0 | 3 | 0 | |
| S | 0 | 12 | 14 | 0 | |
Thus all the four assignment have been made.
The optimal assignment schedule and total time is
| Subordinates | Tasks | Time |
| P | 1 | 8 |
| Q | 3 | 4 |
| R | 2 | 19 |
| S | 4 | 10 |
| Total | 41 | |
The optimum time (minimum) = 41 Hrs.
APPEARS IN
संबंधित प्रश्न
In a factory there are six jobs to be performed each of which should go through two machines A and B in the order A - B. The processing timing (in hours) for the jobs arc given here. You are required to determine the sequence for performing the jobs that would minimize the total elapsed time T. What is the value of T? Also find the idle time for machines · A and B.
| Jobs | J1 | J2 | J3 | J4 | J5 | J6 |
| Machine A | 1 | 3 | 8 | 5 | 6 | 3 |
| MAchine B | 5 | 6 | 3 | 2 | 2 | 10 |
Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 3 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
Choose the correct alternative :
The assignment problem is said to be balanced if it is a ______.
Choose the correct alternative :
In an assignment problem if number of rows is greater than number of columns then
State whether the following is True or False :
In assignment problem, each facility is capable of performing each task.
Give mathematical form of Assignment problem
Find the optimal solution for the assignment problem with the following cost matrix.
| Area | |||||
| 1 | 2 | 3 | 4 | ||
| P | 11 | 17 | 8 | 16 | |
| Salesman | Q | 9 | 7 | 12 | 6 |
| R | 13 | 16 | 15 | 12 | |
| S | 14 | 10 | 12 | 11 | |
Choose the correct alternative:
If number of sources is not equal to number of destinations, the assignment problem is called ______
Choose the correct alternative:
In an assignment problem involving four workers and three jobs, total number of assignments possible are
A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:
| To | |||||||
| 7 | 8 | 9 | 10 | 11 | 12 | ||
| From | 1 | 31 | 62 | 29 | 42 | 15 | 41 |
| 2 | 12 | 19 | 39 | 55 | 71 | 40 | |
| 3 | 17 | 29 | 50 | 41 | 22 | 22 | |
| 4 | 35 | 40 | 38 | 42 | 27 | 33 | |
| 5 | 19 | 30 | 29 | 16 | 20 | 33 | |
| 6 | 72 | 30 | 30 | 50 | 41 | 20 | |
How should the truck be dispersed so as to minimize the total distance travelled?
