Advertisements
Advertisements
प्रश्न
A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 8 | 26 | 17 | 11 |
| Q | 13 | 28 | 4 | 26 | |
| R | 38 | 19 | 18 | 15 | |
| S | 9 | 26 | 24 | 10 | |
How should the tasks be allocated to subordinates so as to minimize the total manhours?
Advertisements
उत्तर
Here the number of rows and columns are equal.
∴ The given assignment problem is balanced.
Step 1: Select the smallest element in each row and subtract this from all the elements in its row.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 18 | 9 | 3 |
| Q | 9 | 24 | 0 | 22 | |
| R | 23 | 4 | 3 | 0 | |
| S | 0 | 17 | 15 | 1 | |
Step 2: Select the smallest element in each column and subtract this from all the elements in its column.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 9 | 20 | 0 | 22 | |
| R | 23 | 0 | 3 | 0 | |
| S | 0 | 13 | 15 | 1 | |
Step 3: (Assignment)
Examine the rows with exactly one zero Mark the zero by □. Mark other zeros in its row by X.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 9 | 20 | 0 | 22 | |
| R | 23 | 0 | 3 | 0 | |
| S | 0 | 13 | 15 | 1 | |
Step 4: Now examine the columns with exactly one zero. Mark the zero by □. Mark other zeros in its row by X.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 9 | 20 | 0 | 22 | |
| R | 23 | 0 | 3 | 0 | |
| S | 0 | 13 | 15 | 1 | |
Step 5: Cover all the zeros of table 4 with three lines, since three assignments were made check (✓) row S since it has no assignment.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 9 | 20 | 0 | 22 | |
| R | 23 | 0 | 3 | 0 | |
| ✓ | S | 0 | 13 | 15 | 1 |
Step 6: Develop the new revised tableau. Examine those elements that are not covered by a line in table 5.
Take the smallest element.
This is 1 (one) our case.
By subtracting 1 from the uncovered cells.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 10 | 20 | 0 | 22 | |
| R | 24 | 0 | 3 | 0 | |
| S | 0 | 12 | 14 | 0 | |
[Adding 1 to elements (Q, S, R) that line at the intersection of two lines]
Step 7: Go to step 3 and repeat the procedure until you arrive at an optimal assignment.
Step 8: Determine an assignment.
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 0 | 14 | 9 | 3 |
| Q | 10 | 20 | 0 | 22 | |
| R | 24 | 0 | 3 | 0 | |
| S | 0 | 12 | 14 | 0 | |
Thus all the four assignment have been made.
The optimal assignment schedule and total time is
| Subordinates | Tasks | Time |
| P | 1 | 8 |
| Q | 3 | 4 |
| R | 2 | 19 |
| S | 4 | 10 |
| Total | 41 | |
The optimum time (minimum) = 41 Hrs.
APPEARS IN
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
|
Jobs
|
Machines |
|||
|
P |
Q |
R |
S |
|
|
Processing Cost (Rs.)
|
||||
|
A |
31 |
25 |
33 |
29 |
|
B |
25 |
24 |
23 |
21 |
|
C |
19 |
21 |
23 |
24 |
|
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
Solve the following minimal assignment problem and hence find minimum time where '- ' indicates that job cannot be assigned to the machine :
| Machines | Processing time in hours | ||||
| A | B | C | D | E | |
| M1 | 9 | 11 | 15 | 10 | 11 |
| M2 | 12 | 9 | - | 10 | 9 |
| M3 | - | 11 | 14 | 11 | 7 |
| M4 | 14 | 8 | 12 | 7 | 8 |
Choose the correct alternative :
In an assignment problem if number of rows is greater than number of columns then
Fill in the blank :
An _______ is a special type of linear programming problem.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
What is the difference between Assignment Problem and Transportation Problem?
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 120 | 100 | 80 |
| 2 | 80 | 90 | 110 | |
| 3 | 110 | 140 | 120 | |
Assign the programmers to the programme in such a way that the total computer time is least.
Choose the correct alternative:
The purpose of a dummy row or column in an assignment problem is to
A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
| I | II | III | IV | V | |
| A | 150 | 120 | 175 | 180 | 200 |
| B | 125 | 110 | 120 | 150 | 165 |
| C | 130 | 100 | 145 | 160 | 170 |
| D | 40 | 40 | 70 | 70 | 100 |
| E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 7 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
