English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 12

A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the

Advertisements
Advertisements

Question

A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:

    Tasks
    1 2 3 4
Subordinates P 8 26 17 11
  Q 13 28 4 26
  R 38 19 18 15
  S 9 26 24 10

How should the tasks be allocated to subordinates so as to minimize the total manhours?

Chart
Sum
Advertisements

Solution

Here the number of rows and columns are equal.

∴ The given assignment problem is balanced.

Step 1: Select the smallest element in each row and subtract this from all the elements in its row.

    Tasks
    1 2 3 4
Subordinates P 0 18 9 3
  Q 9 24 0 22
  R 23 4 3 0
  S 0 17 15 1

Step 2: Select the smallest element in each column and subtract this from all the elements in its column.

    Tasks
    1 2 3 4
Subordinates P 0 14 9 3
  Q 9 20 0 22
  R 23 0 3 0
  S 0 13 15 1

Step 3: (Assignment)
Examine the rows with exactly one zero Mark the zero by □. Mark other zeros in its row by X.

    Tasks
    1 2 3 4
Subordinates P 0 14 9 3
  Q 9 20 0 22
  R 23 0 3 0
  S 0 13 15 1

Step 4: Now examine the columns with exactly one zero. Mark the zero by □. Mark other zeros in its row by X.

    Tasks
    1 2 3 4
Subordinates P 0 14 9 3
  Q 9 20 0 22
  R 23 0 3 0
  S 0 13 15 1

Step 5: Cover all the zeros of table 4 with three lines, since three assignments were made check (✓) row S since it has no assignment.

    Tasks
    1 2 3 4
Subordinates P 0 14 9 3
  Q 9 20 0 22
  R 23 0 3 0
✓ S 0 13 15 1

Step 6: Develop the new revised tableau. Examine those elements that are not covered by a line in table 5.

Take the smallest element.

This is 1 (one) our case.

By subtracting 1 from the uncovered cells.

    Tasks
    1 2 3 4
Subordinates P 0 14 9 3
  Q 10 20 0 22
  R 24 0 3 0
  S 0 12 14 0

[Adding 1 to elements (Q, S, R) that line at the intersection of two lines]

Step 7: Go to step 3 and repeat the procedure until you arrive at an optimal assignment.

Step 8: Determine an assignment.

    Tasks
    1 2 3 4
Subordinates P 0 14 9 3
  Q 10 20 0 22
  R 24 0 3 0
  S 0 12 14 0

Thus all the four assignment have been made.

The optimal assignment schedule and total time is

Subordinates Tasks Time
P 1 8
Q 3 4
R 2 19
S 4 10
Total 41

The optimum time (minimum) = 41 Hrs.

shaalaa.com
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.2 [Page 256]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 12 TN Board
Chapter 10 Operations Research
Exercise 10.2 | Q 6 | Page 256

RELATED QUESTIONS

Solve the following minimal assignment problem : 

Machines A B C D E
M1 27 18 ∞ 20 21
M2 31 24 21 12 17
M3 20 17 20 ∞ 16
M4 21 28 20 16 27

Solve the following minimal assignment problem and hence find minimum time where  '- ' indicates that job cannot be assigned to the machine : 

Machines Processing time in hours
A B C D E
M1 9 11 15 10 11
M2 12 9 - 10 9
M3 - 11 14 11 7
M4 14 8 12 7 8

In a factory there are six jobs to be performed each of which should go through two machines A and B in the order A - B. The processing timing (in hours) for the jobs arc given here. You are required to determine the sequence for performing the jobs that would minimize the total elapsed time T. What is the value of T? Also find the idle time for machines · A and B.

Jobs J1 J2 J3 J4 J5 J6
Machine A 1 3 8 5 6 3
MAchine B 5 6 3 2 2 10

The objective of an assignment problem is to assign ______. 


Choose the correct alternative:

When an assignment problem has more than one solution, then it is ______


In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added


State whether the following statement is True or False:

In assignment problem, if number of columns is greater than number of rows, then a dummy row is added


Choose the correct alternative:

The purpose of a dummy row or column in an assignment problem is to


A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:

    To
    7 8 9 10 11 12
From 1 31 62 29 42 15 41
2 12 19 39 55 71 40
3 17 29 50 41 22 22
4 35 40 38 42 27 33
5 19 30 29 16 20 33
6 72 30 30 50 41 20

How should the truck be dispersed so as to minimize the total distance travelled?


A department store has four workers to pack goods. The times (in minutes) required for each worker to complete the packings per item sold is given below. How should the manager of the store assign the jobs to the workers, so as to minimize the total time of packing?

Workers Packing of
  Books Toys Crockery Cutlery
A 3 11 10 8
B 13 2 12 12
C 3 4 6 1
D 4 15 4 9

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×