Advertisements
Advertisements
प्रश्न
Choose the correct alternative:
When an assignment problem has more than one solution, then it is ______
विकल्प
double optimal solution
infinite optimal solution
multiple optimal solution
dual optimal solution
Advertisements
उत्तर
multiple optimal solution
APPEARS IN
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
|
Jobs
|
Machines |
|||
|
P |
Q |
R |
S |
|
|
Processing Cost (Rs.)
|
||||
|
A |
31 |
25 |
33 |
29 |
|
B |
25 |
24 |
23 |
21 |
|
C |
19 |
21 |
23 |
24 |
|
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
Service Time ( in hrs.)
| Counters | Salesmen | |||
| A | B | C | D | |
| W | 41 | 72 | 39 | 52 |
| X | 22 | 29 | 49 | 65 |
| Y | 27 | 39 | 60 | 51 |
| Z | 45 | 50 | 48 | 52 |
Solve the following minimal assignment problem :
| Machines | A | B | C | D | E |
| M1 | 27 | 18 | ∞ | 20 | 21 |
| M2 | 31 | 24 | 21 | 12 | 17 |
| M3 | 20 | 17 | 20 | ∞ | 16 |
| M4 | 21 | 28 | 20 | 16 | 27 |
Determine `l_92 and l_93, "given that" l_91 = 97, d_91 = 38 and q_92 = 27/59`
Solve the following maximal assignment problem :
| Branch Manager | Monthly Business ( Rs. lakh) | |||
| A | B | C | D | |
| P | 11 | 11 | 9 | 9 |
| Q | 13 | 16 | 11 | 10 |
| R | 12 | 17 | 13 | 8 |
| S | 16 | 14 | 16 | 12 |
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:
| Jobs | Machines (Processing Cost in ₹) |
|||
| P | Q | R | S | |
| A | 31 | 25 | 33 | 29 |
| B | 25 | 24 | 23 | 21 |
| C | 19 | 21 | 23 | 24 |
| D | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:
| Job | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 30 | 37 | 40 | 28 | 40 |
| 2 | 40 | 24 | 27 | 21 | 36 |
| 3 | 40 | 32 | 33 | 30 | 35 |
| 4 | 25 | 38 | 40 | 36 | 36 |
| 5 | 29 | 62 | 41 | 34 | 39 |
Find the optimal assignment schedule.
The assignment problem is said to be unbalance if ______
The objective of an assignment problem is to assign ______.
State whether the following is True or False :
In assignment problem, each facility is capable of performing each task.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
Solve the following problem :
A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.
| I | II | III | IV | |
| A | 7 | 25 | 26 | 10 |
| B | 12 | 27 | 3 | 25 |
| C | 37 | 18 | 17 | 14 |
| D | 18 | 25 | 23 | 9 |
How should the tasks be allocated, one to a man, as to minimize the total man hours?
Solve the following problem :
A dairy plant has five milk tankers, I, II, III, IV and V. These milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
| I | II | III | IV | V | |
| A | 150 | 120 | 175 | 180 | 200 |
| B | 125 | 110 | 120 | 150 | 165 |
| C | 130 | 100 | 145 | 160 | 175 |
| D | 40 | 40 | 70 | 70 | 100 |
| E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added
What is the Assignment problem?
What is the difference between Assignment Problem and Transportation Problem?
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 120 | 100 | 80 |
| 2 | 80 | 90 | 110 | |
| 3 | 110 | 140 | 120 | |
Assign the programmers to the programme in such a way that the total computer time is least.
Assign four trucks 1, 2, 3 and 4 to vacant spaces A, B, C, D, E and F so that distance travelled is minimized. The matrix below shows the distance.
| 1 | 2 | 3 | 4 | |
| A | 4 | 7 | 3 | 7 |
| B | 8 | 2 | 5 | 5 |
| C | 4 | 9 | 6 | 9 |
| D | 7 | 5 | 4 | 8 |
| E | 6 | 3 | 5 | 4 |
| F | 6 | 8 | 7 | 3 |
Choose the correct alternative:
Number of basic allocation in any row or column in an assignment problem can be
Choose the correct alternative:
North – West Corner refers to ______
Choose the correct alternative:
If number of sources is not equal to number of destinations, the assignment problem is called ______
Choose the correct alternative:
In an assignment problem involving four workers and three jobs, total number of assignments possible are
A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:
| To | |||||||
| 7 | 8 | 9 | 10 | 11 | 12 | ||
| From | 1 | 31 | 62 | 29 | 42 | 15 | 41 |
| 2 | 12 | 19 | 39 | 55 | 71 | 40 | |
| 3 | 17 | 29 | 50 | 41 | 22 | 22 | |
| 4 | 35 | 40 | 38 | 42 | 27 | 33 | |
| 5 | 19 | 30 | 29 | 16 | 20 | 33 | |
| 6 | 72 | 30 | 30 | 50 | 41 | 20 | |
How should the truck be dispersed so as to minimize the total distance travelled?
A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
| I | II | III | IV | V | |
| A | 150 | 120 | 175 | 180 | 200 |
| B | 125 | 110 | 120 | 150 | 165 |
| C | 130 | 100 | 145 | 160 | 170 |
| D | 40 | 40 | 70 | 70 | 100 |
| E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 31 | 25 | 33 | 29 |
| Q | 25 | 24 | 23 | 21 |
| R | 19 | 21 | 23 | 24 |
| S | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:
| I | II | III | IV | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Complete the following activity to allocate tasks to subordinates to minimize total time.
Solution:
Step I: Subtract the smallest element of each row from every element of that row:
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Step II: Since all column minimums are zero, no need to subtract anything from columns.
Step III: Draw the minimum number of lines to cover all zeros.
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Since minimum number of lines = order of matrix, optimal solution has been reached
Optimal assignment is A →`square` B →`square`
C →IV D →`square`
Total minimum time = `square` hours.