हिंदी

Suggest Optimum Solution to the Following Assignment. Problem, Also Find the Total Minimum Service Time. Service Time ( in Hrs.) - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
                                             Service Time ( in hrs.)

Counters Salesmen
A B C D
W 41 72 39 52
X 22 29 49 65
Y 27 39 60 51
Z 45 50 48 52
योग
Advertisements

उत्तर

This problem is already 4 x 4.
Select the smallest element in each row and subtract it from every element in each row :


Select the smallest element in each column of the above matrix and subtract it form every element in that column.

Draw the minimum lines covering all zeros.

Minimum lines covering all zeros is not equal to the order of the matrix.
Minimum uncovered value 2 is subtracted from uncovered values and added to values at intersection of the lines.


Draw minimum lines covering all the zeros.

Minimum lines covering all the zeros equal to the order of the matrix.
∴ Allocation of counters can be done.


The allocation of the counters to the  salesmen is
W → C, X → B, Y → A, Z → D

The minimum time = 39 + 29 + 27 +52 = 147 Hrs.

shaalaa.com
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
2018-2019 (March) Set 1

APPEARS IN

वीडियो ट्यूटोरियलVIEW ALL [1]

संबंधित प्रश्न

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:

         Jobs

 

 

                          Machines

P

Q

R

S

                Processing Cost (Rs.)

 

A

31

25

33

29

B

25

24

23

21

C

19

21

23

24

D

38

36

34

40

 How should the jobs be assigned to the four machines so that the total processing cost is minimum?


Determine `l_92 and l_93, "given that"  l_91 = 97, d_91 = 38 and q_92 = 27/59`


Solve the following minimal assignment problem and hence find minimum time where  '- ' indicates that job cannot be assigned to the machine : 

Machines Processing time in hours
A B C D E
M1 9 11 15 10 11
M2 12 9 - 10 9
M3 - 11 14 11 7
M4 14 8 12 7 8

Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?

  I II III IV V
1 10 5 9 18 11
2 13 9 6 12 14
3 3 2 4 4 5
4 18 9 12 17 15
5 11 6 14 19 10

Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:

Job Machines (Profit in ₹)
A B C D E
1 30 37 40 28 40
2 40 24 27 21 36
3 40 32 33 30 35
4 25 38 40 36 36
5 29 62 41 34 39

Find the optimal assignment schedule.


The assignment problem is said to be unbalance if ______


Choose the correct alternative :

The assignment problem is said to be balanced if it is a ______.


Fill in the blank :

When an assignment problem has more than one solution, then it is _______ optimal solution.


In an assignment problem, if number of column is greater than number of rows, then a dummy column is added.


Solve the following problem :

A dairy plant has five milk tankers, I, II, III, IV and V. These milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.

  I II III IV V
A 150 120 175 180 200
B 125 110 120 150 165
C 130 100 145 160 175
D 40 40 70 70 100
E 45 25 60 70 95

How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?


Choose the correct alternative:

The assignment problem is generally defined as a problem of ______


Choose the correct alternative: 

Assignment Problem is special case of ______


In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added


State whether the following statement is True or False:

In assignment problem, if number of columns is greater than number of rows, then a dummy row is added


Choose the correct alternative:

Number of basic allocation in any row or column in an assignment problem can be


Choose the correct alternative:

If number of sources is not equal to number of destinations, the assignment problem is called ______


Choose the correct alternative:

The solution for an assignment problem is optimal if


Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?

  I II III IV V
1 10 5 9 18 11
2 13 9 6 12 14
3 7 2 4 4 5
4 18 9 12 17 15
5 11 6 14 19 10

A job production unit has four jobs P, Q, R, S which can be manufactured on each of the four machines I, II, III and IV. The processing cost of each job for each machine is given in the following table :

Job Machines
(Processing cost in ₹)
I II III IV
P 31 25 33 29
Q 25 24 23 21
R 19 21 23 24
S 38 36 34 40

Complete the following activity to find the optimal assignment to minimize the total processing cost.

Solution:

Step 1: Subtract the smallest element in each row from every element of it. New assignment matrix is obtained as follows :

Job Machines
(Processing cost in ₹)
I II III IV
P 6 0 8 4
Q 4 3 2 0
R 0 2 4 5
S 4 2 0 6

Step 2: Subtract the smallest element in each column from every element of it. New assignment matrix is obtained as above, because each column in it contains one zero.

Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros:

Job Machines
(Processing cost in ₹)
I II III IV
P 6 0 8 4
Q 4 3 2 0
R 0 2 4 5
S 4 2 0 6

Step 4: From step 3, as the minimum number of straight lines required to cover all zeros in the assignment matrix equals the number of rows/columns. Optimal solution has reached.

Examine the rows one by one starting with the first row with exactly one zero is found. Mark the zero by enclosing it in (`square`), indicating assignment of the job. Cross all the zeros in the same column. This step is shown in the following table :

Job Machines
(Processing cost in ₹)
I II III IV
P 6 0 8 4
Q 4 3 2 0
R 0 2 4 5
S 4 2 0 6

Step 5: It is observed that all the zeros are assigned and each row and each column contains exactly one assignment. Hence, the optimal (minimum) assignment schedule is :

Job Machine Min.cost
P II `square`
Q `square` 21
R I `square`
S III 34

Hence, total (minimum) processing cost = 25 + 21 + 19 + 34 = ₹`square`


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×