Advertisements
Advertisements
प्रश्न
Solve the following problem :
A dairy plant has five milk tankers, I, II, III, IV and V. These milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
| I | II | III | IV | V | |
| A | 150 | 120 | 175 | 180 | 200 |
| B | 125 | 110 | 120 | 150 | 165 |
| C | 130 | 100 | 145 | 160 | 175 |
| D | 40 | 40 | 70 | 70 | 100 |
| E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
Advertisements
उत्तर
Step 1: Row minimum
Subtract the smallest element in each row from every element in its row.
The matrix obtained is given below:
| I | II | III | IV | V | |
| A | 30 | 0 | 55 | 60 | 80 |
| B | 15 | 0 | 10 | 40 | 55 |
| C | 30 | 0 | 45 | 60 | 75 |
| D | 0 | 0 | 30 | 30 | 60 |
| E | 20 | 0 | 35 | 45 | 70 |
Step 2: Column minimum
Subtract the smallest element in each column of assignment matrix obtained in step 1 from every element in its column.
| I | II | III | IV | V | |
| A | 30 | 0 | 45 | 30 | 25 |
| B | 15 | 0 | 0 | 10 | 0 |
| C | 30 | 0 | 35 | 30 | 20 |
| D | 0 | 0 | 20 | 0 | 5 |
| E | 20 | 0 | 25 | 15 | 15 |
Step 3:
Draw minimum number of vertical and horizontal lines to cover all zeros.
First cover all rows and columns which have maximum number of zeros.
| I | II | III | IV | V | |
| A | 30 | 0 | 45 | 30 | 25 |
| B | 15 | 0 | 0 | 10 | 0 |
| C | 30 | 0 | 35 | 30 | 20 |
| D | 0 | 0 | 20 | 0 | 5 |
| E | 20 | 0 | 25 | 15 | 15 |
Step 4:
From step 3, minimum number of lines covering all the zeros are 3, which is less than order of matrix, i.e., 5.
∴ Select smallest element from all the uncovered elements, i.e., 15 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
| I | II | III | IV | V | |
| A | 15 | 0 | 30 | 15 | 10 |
| B | 15 | 15 | 0 | 10 | 0 |
| C | 15 | 0 | 20 | 15 | 5 |
| D | 0 | 15 | 20 | 0 | 5 |
| E | 5 | 0 | 10 | 0 | 0 |
Step 5:
Draw minimum number of vertical and horizontal lines to cover all zeros.
| I | II | III | IV | V | |
| A | 15 | 0 | 30 | 15 | 10 |
| B | 15 | 15 | 0 | 10 | 0 |
| C | 15 | 0 | 20 | 15 | 5 |
| D | 0 | 15 | 20 | 0 | 5 |
| E | 5 | 0 | 10 | 0 | 0 |
Step 6:
From step 5, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e., 5.
∴ Select smallest element from all the uncovered elements, i.e., 5 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
| I | II | III | IV | V | |
| A | 10 | 0 | 25 | 10 | 5 |
| B | 15 | 20 | 0 | 10 | 0 |
| C | 10 | 0 | 15 | 10 | 0 |
| D | 0 | 20 | 20 | 0 | 5 |
| E | 5 | 5 | 10 | 0 | 0 |
Step 7:
Draw minimum number of vertical and horizontal lines to cover all zeros.
| I | II | III | IV | V | |
| A | 10 | 0 | 25 | 10 | 5 |
| B | 15 | 20 | 0 | 10 | 0 |
| C | 10 | 0 | 15 | 10 | 0 |
| D | 0 | 20 | 20 | 0 | 5 |
| E | 5 | 5 | 10 | 0 | 0 |
Step 8:
From step 7, minimum number of lines covering all the zeros are 5, which is equal to order of the matrix, i.e., 5.
∴ Select a row with exactly one zero, enclose that zero in () and cross out all zeros in its respective column.
Similarly, examine each row and column and mark the assignment ().
∴ The matrix obtained is as follows:
| I | II | III | IV | V | |
| A | 10 | 0 | 25 | 10 | 5 |
| B | 15 | 20 | 0 | 10 | 0 |
| C | 10 | 0 | 15 | 10 | 0 |
| D | 0 | 20 | 20 | 0 | 5 |
| E | 5 | 5 | 10 | 0 | 0 |
Step 9:
The matrix obtained in step 8 contains exactly one assignment for each row and column.
∴ Optimal assignment schedule is as follows:
| Routes | Dairy Plant | Distance (kms) |
| A | II | 120 |
| B | III | 120 |
| C | V | 175 |
| D | I | 40 |
| E | IV | 70 |
| 525 |
∴ Minimum distance travelled
= 120 + 120 + 175 + 40 + 70
= 525 kms.
APPEARS IN
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
|
Jobs
|
Machines |
|||
|
P |
Q |
R |
S |
|
|
Processing Cost (Rs.)
|
||||
|
A |
31 |
25 |
33 |
29 |
|
B |
25 |
24 |
23 |
21 |
|
C |
19 |
21 |
23 |
24 |
|
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
Solve the following minimal assignment problem and hence find the minimum value :
| I | II | III | IV | |
| A | 2 | 10 | 9 | 7 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
Service Time ( in hrs.)
| Counters | Salesmen | |||
| A | B | C | D | |
| W | 41 | 72 | 39 | 52 |
| X | 22 | 29 | 49 | 65 |
| Y | 27 | 39 | 60 | 51 |
| Z | 45 | 50 | 48 | 52 |
Solve the following maximal assignment problem :
| Branch Manager | Monthly Business ( Rs. lakh) | |||
| A | B | C | D | |
| P | 11 | 11 | 9 | 9 |
| Q | 13 | 16 | 11 | 10 |
| R | 12 | 17 | 13 | 8 |
| S | 16 | 14 | 16 | 12 |
Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:
| Job | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 30 | 37 | 40 | 28 | 40 |
| 2 | 40 | 24 | 27 | 21 | 36 |
| 3 | 40 | 32 | 33 | 30 | 35 |
| 4 | 25 | 38 | 40 | 36 | 36 |
| 5 | 29 | 62 | 41 | 34 | 39 |
Find the optimal assignment schedule.
The assignment problem is said to be balanced if ______.
Choose the correct alternative :
The assignment problem is said to be balanced if it is a ______.
Choose the correct alternative :
In an assignment problem if number of rows is greater than number of columns then
In an assignment problem, if number of column is greater than number of rows, then a dummy column is added.
State whether the following is True or False :
In assignment problem, each facility is capable of performing each task.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
Choose the correct alternative:
When an assignment problem has more than one solution, then it is ______
Choose the correct alternative:
The assignment problem is said to be balanced if ______
If the given matrix is ______ matrix, the assignment problem is called balanced problem
In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added
State whether the following statement is True or False:
In assignment problem, if number of columns is greater than number of rows, then a dummy row is added
Give mathematical form of Assignment problem
What is the difference between Assignment Problem and Transportation Problem?
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 120 | 100 | 80 |
| 2 | 80 | 90 | 110 | |
| 3 | 110 | 140 | 120 | |
Assign the programmers to the programme in such a way that the total computer time is least.
A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 8 | 26 | 17 | 11 |
| Q | 13 | 28 | 4 | 26 | |
| R | 38 | 19 | 18 | 15 | |
| S | 9 | 26 | 24 | 10 | |
How should the tasks be allocated to subordinates so as to minimize the total manhours?
Assign four trucks 1, 2, 3 and 4 to vacant spaces A, B, C, D, E and F so that distance travelled is minimized. The matrix below shows the distance.
| 1 | 2 | 3 | 4 | |
| A | 4 | 7 | 3 | 7 |
| B | 8 | 2 | 5 | 5 |
| C | 4 | 9 | 6 | 9 |
| D | 7 | 5 | 4 | 8 |
| E | 6 | 3 | 5 | 4 |
| F | 6 | 8 | 7 | 3 |
Choose the correct alternative:
North – West Corner refers to ______
A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:
| To | |||||||
| 7 | 8 | 9 | 10 | 11 | 12 | ||
| From | 1 | 31 | 62 | 29 | 42 | 15 | 41 |
| 2 | 12 | 19 | 39 | 55 | 71 | 40 | |
| 3 | 17 | 29 | 50 | 41 | 22 | 22 | |
| 4 | 35 | 40 | 38 | 42 | 27 | 33 | |
| 5 | 19 | 30 | 29 | 16 | 20 | 33 | |
| 6 | 72 | 30 | 30 | 50 | 41 | 20 | |
How should the truck be dispersed so as to minimize the total distance travelled?
A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 31 | 25 | 33 | 29 |
| Q | 25 | 24 | 23 | 21 |
| R | 19 | 21 | 23 | 24 |
| S | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
A department store has four workers to pack goods. The times (in minutes) required for each worker to complete the packings per item sold is given below. How should the manager of the store assign the jobs to the workers, so as to minimize the total time of packing?
| Workers | Packing of | |||
| Books | Toys | Crockery | Cutlery | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 12 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:
| I | II | III | IV | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Complete the following activity to allocate tasks to subordinates to minimize total time.
Solution:
Step I: Subtract the smallest element of each row from every element of that row:
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Step II: Since all column minimums are zero, no need to subtract anything from columns.
Step III: Draw the minimum number of lines to cover all zeros.
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Since minimum number of lines = order of matrix, optimal solution has been reached
Optimal assignment is A →`square` B →`square`
C →IV D →`square`
Total minimum time = `square` hours.
