Advertisements
Advertisements
Question
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
|
Jobs
|
Machines |
|||
|
P |
Q |
R |
S |
|
|
Processing Cost (Rs.)
|
||||
|
A |
31 |
25 |
33 |
29 |
|
B |
25 |
24 |
23 |
21 |
|
C |
19 |
21 |
23 |
24 |
|
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
Advertisements
Solution
We can express the matrix form
`[(31,25,33,29), (25,24,23,21), (19,21,23,24), (38,36,34,40)]`
Subtracting the smallest element in each row from every element of it,
`[(6,0,8,4), (4,3,2,0), (0,2,4,5), (4,2,0,6)]`
Subtracting the smallest element In each column from very element of it.
`[(6,0,8,4), (4,3,2,0), (0,2,4,5), (4,2,0,6)]`
All the zeros of the above matrix are covered with minimum number of lines as below :

No. of lines = No. of rows/columns

Assignment of jobs :
A → Q, B → S, C → P, D → R
Minimum cost = 25 + 21 + 19 + 34
= Rs 99
APPEARS IN
RELATED QUESTIONS
Solve the following minimal assignment problem :
| Machines | A | B | C | D | E |
| M1 | 27 | 18 | ∞ | 20 | 21 |
| M2 | 31 | 24 | 21 | 12 | 17 |
| M3 | 20 | 17 | 20 | ∞ | 16 |
| M4 | 21 | 28 | 20 | 16 | 27 |
Solve the following maximal assignment problem :
| Branch Manager | Monthly Business ( Rs. lakh) | |||
| A | B | C | D | |
| P | 11 | 11 | 9 | 9 |
| Q | 13 | 16 | 11 | 10 |
| R | 12 | 17 | 13 | 8 |
| S | 16 | 14 | 16 | 12 |
Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:
| Job | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 30 | 37 | 40 | 28 | 40 |
| 2 | 40 | 24 | 27 | 21 | 36 |
| 3 | 40 | 32 | 33 | 30 | 35 |
| 4 | 25 | 38 | 40 | 36 | 36 |
| 5 | 29 | 62 | 41 | 34 | 39 |
Find the optimal assignment schedule.
Choose the correct alternative :
The assignment problem is said to be balanced if it is a ______.
Choose the correct alternative :
In an assignment problem if number of rows is greater than number of columns then
Fill in the blank :
An _______ is a special type of linear programming problem.
State whether the following is True or False :
In assignment problem, each facility is capable of performing each task.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
Choose the correct alternative:
Assignment Problem is special case of ______
Choose the correct alternative:
The assignment problem is said to be balanced if ______
In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 120 | 100 | 80 |
| 2 | 80 | 90 | 110 | |
| 3 | 110 | 140 | 120 | |
Assign the programmers to the programme in such a way that the total computer time is least.
A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 8 | 26 | 17 | 11 |
| Q | 13 | 28 | 4 | 26 | |
| R | 38 | 19 | 18 | 15 | |
| S | 9 | 26 | 24 | 10 | |
How should the tasks be allocated to subordinates so as to minimize the total manhours?
Choose the correct alternative:
The purpose of a dummy row or column in an assignment problem is to
Choose the correct alternative:
In an assignment problem involving four workers and three jobs, total number of assignments possible are
A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:
| To | |||||||
| 7 | 8 | 9 | 10 | 11 | 12 | ||
| From | 1 | 31 | 62 | 29 | 42 | 15 | 41 |
| 2 | 12 | 19 | 39 | 55 | 71 | 40 | |
| 3 | 17 | 29 | 50 | 41 | 22 | 22 | |
| 4 | 35 | 40 | 38 | 42 | 27 | 33 | |
| 5 | 19 | 30 | 29 | 16 | 20 | 33 | |
| 6 | 72 | 30 | 30 | 50 | 41 | 20 | |
How should the truck be dispersed so as to minimize the total distance travelled?
A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 31 | 25 | 33 | 29 |
| Q | 25 | 24 | 23 | 21 |
| R | 19 | 21 | 23 | 24 |
| S | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
A department store has four workers to pack goods. The times (in minutes) required for each worker to complete the packings per item sold is given below. How should the manager of the store assign the jobs to the workers, so as to minimize the total time of packing?
| Workers | Packing of | |||
| Books | Toys | Crockery | Cutlery | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 12 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
