English

A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E.

Advertisements
Advertisements

Question

A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.

  I II III IV V
A 150 120 175 180 200
B 125 110 120 150 165
C 130 100 145 160 170
D 40 40 70 70 100
E 45 25 60 70 95

How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?

Chart
Sum
Advertisements

Solution

Step 1: Row minimum

Subtract the smallest element in each row from every element in its row.

The matrix obtained is given below:

  I II III IV V
A 30 0 55 60 80
B 15 0 10 40 55
C 30 0 45 60 70
D 0 0 30 30 60
E 20 0 35 45 70

Step 2: Column minimum

Subtract the smallest element in each column of assignment matrix obtained in step 1 from every element in its column.

  I II III IV V
A 30 0 45 30 25
B 15 0 0 10 0
C 30 0 35 30 15
D 0 0 20 0 5
E 20 0 25 15 15

Step 3:

Draw minimum number of vertical and horizontal lines to cover all zeros. 

First cover all rows and columns which have maximum number of zeros.

  I II III IV V
A 30 0 45 30 25
B 15 0 0 10 0
C 30 0 35 30 15
D 0 0 20 0 5
E 20 0 25 15 15

Step 4:

From step 3, minimum number of lines covering all the zeros are 3, which is less than order of matrix, i.e., 5.

∴  Select smallest element from all the uncovered elements, i.e., 15 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.

  I II III IV V
A 15 0 30 15 10
B 15 15 0 10 0
C 15 0 20 15 0
D 0 15 20 0 5
E 5 0 10 0 0

Step 5:

Draw minimum number of vertical and horizontal lines to cover all zeros.

  I II III IV V
A 15 0 30 15 10
B 15 15 0 10 0
C 15 0 20 15 0
D 0 15 20 0 5
E 5 0 10 0 0

Step 6:

From step 5, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e., 5.

∴ Select a row with exactly one zero, enclose that zero in () and cross out all zeros in its respective column.

Similarly, examine each row and column and mark the assignment ().

∴ The matrix obtained is as follows:

  I II III IV V
A 15 0 30 15 10
B 15 15 0 10 0
C 15 0 20 15 0
D 0 15 20 0 5
E 5 0 10 0 0

Step 7:

The matrix obtained in step 6 contains exactly one assignment for each row and column.

∴ Optimal assignment schedule is as follows:

Routes Dairy Plant Distance (kms)
A II 120
B III 120
C V 170
D I 40
E IV 70
    520

∴ Minimum distance travelled

= 120 + 120 + 170 + 40 + 70

= 520 kms.

shaalaa.com
  Is there an error in this question or solution?
Chapter 2.7: Assignment Problem and Sequencing - Q.4

Video TutorialsVIEW ALL [1]

RELATED QUESTIONS

Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
                                             Service Time ( in hrs.)

Counters Salesmen
A B C D
W 41 72 39 52
X 22 29 49 65
Y 27 39 60 51
Z 45 50 48 52

Determine `l_92 and l_93, "given that"  l_91 = 97, d_91 = 38 and q_92 = 27/59`


Solve the following minimal assignment problem and hence find minimum time where  '- ' indicates that job cannot be assigned to the machine : 

Machines Processing time in hours
A B C D E
M1 9 11 15 10 11
M2 12 9 - 10 9
M3 - 11 14 11 7
M4 14 8 12 7 8

Solve the following maximal assignment problem :

Branch Manager Monthly Business ( Rs. lakh)
A B C D
P 11 11 9 9
Q 13 16 11 10
R 12 17 13 8
S 16 14 16 12

 


A departmental head has three jobs and four subordinates. The subordinates differ in their capabilities and the jobs differ in their work
contents. With the help of the performance matrix given below, find out which of the four subordinates should be assigned which jobs ?

Subordinates Jobs
I II III
A 7 3 5
B 2 7 4
C 6 5 3
D 3 4 7

Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?

  I II III IV V
1 10 5 9 18 11
2 13 9 6 12 14
3 3 2 4 4 5
4 18 9 12 17 15
5 11 6 14 19 10

Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:

Job Machines (Profit in ₹)
A B C D E
1 30 37 40 28 40
2 40 24 27 21 36
3 40 32 33 30 35
4 25 38 40 36 36
5 29 62 41 34 39

Find the optimal assignment schedule.


The assignment problem is said to be unbalance if ______


Choose the correct alternative :

In an assignment problem if number of rows is greater than number of columns then


Fill in the blank :

When an assignment problem has more than one solution, then it is _______ optimal solution.


In an assignment problem, if number of column is greater than number of rows, then a dummy column is added.


State whether the following is True or False :

In assignment problem, each facility is capable of performing each task.


Solve the following problem :

A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.

  I II III IV
A 7 25 26 10
B 12 27 3 25
C 37 18 17 14
D 18 25 23 9

How should the tasks be allocated, one to a man, as to minimize the total man hours?


Choose the correct alternative:

The assignment problem is generally defined as a problem of ______


Choose the correct alternative:

The assignment problem is said to be balanced if ______


If the given matrix is ______ matrix, the assignment problem is called balanced problem


State whether the following statement is True or False:

In assignment problem, if number of columns is greater than number of rows, then a dummy row is added


State whether the following statement is True or False: 

In assignment problem each worker or machine is assigned only one job


What is the difference between Assignment Problem and Transportation Problem?


A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:

    Tasks
    1 2 3 4
Subordinates P 8 26 17 11
  Q 13 28 4 26
  R 38 19 18 15
  S 9 26 24 10

How should the tasks be allocated to subordinates so as to minimize the total manhours?


Choose the correct alternative:

If number of sources is not equal to number of destinations, the assignment problem is called ______


Choose the correct alternative:

The purpose of a dummy row or column in an assignment problem is to


A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:

    To
    7 8 9 10 11 12
From 1 31 62 29 42 15 41
2 12 19 39 55 71 40
3 17 29 50 41 22 22
4 35 40 38 42 27 33
5 19 30 29 16 20 33
6 72 30 30 50 41 20

How should the truck be dispersed so as to minimize the total distance travelled?


A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:

Job Machines
(Processing cost in ₹)
I II III IV
P 31 25 33 29
Q 25 24 23 21
R 19 21 23 24
S 38 36 34 40

Find the optimal assignment to minimize the total processing cost.


Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?

  I II III IV V
1 10 5 9 18 11
2 13 9 6 12 14
3 7 2 4 4 5
4 18 9 12 17 15
5 11 6 14 19 10

A job production unit has four jobs P, Q, R, S which can be manufactured on each of the four machines I, II, III and IV. The processing cost of each job for each machine is given in the following table :

Job Machines
(Processing cost in ₹)
I II III IV
P 31 25 33 29
Q 25 24 23 21
R 19 21 23 24
S 38 36 34 40

Complete the following activity to find the optimal assignment to minimize the total processing cost.

Solution:

Step 1: Subtract the smallest element in each row from every element of it. New assignment matrix is obtained as follows :

Job Machines
(Processing cost in ₹)
I II III IV
P 6 0 8 4
Q 4 3 2 0
R 0 2 4 5
S 4 2 0 6

Step 2: Subtract the smallest element in each column from every element of it. New assignment matrix is obtained as above, because each column in it contains one zero.

Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros:

Job Machines
(Processing cost in ₹)
I II III IV
P 6 0 8 4
Q 4 3 2 0
R 0 2 4 5
S 4 2 0 6

Step 4: From step 3, as the minimum number of straight lines required to cover all zeros in the assignment matrix equals the number of rows/columns. Optimal solution has reached.

Examine the rows one by one starting with the first row with exactly one zero is found. Mark the zero by enclosing it in (`square`), indicating assignment of the job. Cross all the zeros in the same column. This step is shown in the following table :

Job Machines
(Processing cost in ₹)
I II III IV
P 6 0 8 4
Q 4 3 2 0
R 0 2 4 5
S 4 2 0 6

Step 5: It is observed that all the zeros are assigned and each row and each column contains exactly one assignment. Hence, the optimal (minimum) assignment schedule is :

Job Machine Min.cost
P II `square`
Q `square` 21
R I `square`
S III 34

Hence, total (minimum) processing cost = 25 + 21 + 19 + 34 = ₹`square`


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×