English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 12

A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in

Advertisements
Advertisements

Question

A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:

    To
    7 8 9 10 11 12
From 1 31 62 29 42 15 41
2 12 19 39 55 71 40
3 17 29 50 41 22 22
4 35 40 38 42 27 33
5 19 30 29 16 20 33
6 72 30 30 50 41 20

How should the truck be dispersed so as to minimize the total distance travelled?

Chart
Sum
Advertisements

Solution

Here the number of rows and columns are equal.

∴ The given assignment problem is balanced.

Step 1: Select the smallest element in each row and subtract this from all the elements in its row.

    To
    7 8 9 10 11 12
From 1 16 47 14 27 0 26
2 0 7 27 43 59 28
3 0 12 33 24 5 5
4 8 13 11 15 0 6
5 3 14 13 0 4 17
6 52 10 10 30 21 0

Step 2: Select the smallest element in each column and subtract this from all the elements in its column.

    To
    7 8 9 10 11 12
From 1 16 40 4 27 0 26
2 0 0 17 43 59 28
3 0 5 23 24 5 5
4 8 6 1 15 0 6
5 3 7 3 0 4 17
6 52 3 0 30 21 0

Step 3: Examine the rows with exactly one zero, mark the zero by □ mark other zeros, in its column by X

    To
    7 8 9 10 11 12
From 1 16 40 4 27 0 26
2 0 0 17 43 59 28
3 0 5 23 24 5 5
4 8 6 1 15 0 6
5 3 7 3 0 4 17
6 52 3 0 30 21 0

Step 4: Examine the Columns with exactly one zero. If there is exactly one zero, mark that zero by □ mark other zeros in its rows by X

    To
    7 8 9 10 11 12
From 1 16 40 4 27 0 26
2 0 0 17 43 59 28
3 0 5 23 24 5 5
4 8 6 1 15 0 6
5 3 7 3 0 4 17
6 52 3 0 30 21 0

Step 5: Cover all the zeros of table 4 with five lines. Since three assignments were made

    To
    7 8 9 10 11 12
From 1 16 40 4 27 0 26
2 0 0 17 43 59 28
3 0 5 23 24 5 5
4 8 6 1 15 0 6
5 3 7 3 0 4 17
6 52 3 0 30 21 0

Step 6: Develop the new revised tableau. Examine those elements that are not covered by a line in Table 5. Take the smallest element. This is l(one) in our case. By subtracting 1 from the uncovered cells.

    To
    7 8 9 10 11 12
From 1 16 40 4 27 0 26
2 0 0 17 43 59 28
3 0 5 23 24 5 5
4 8 6 1 15 0 6
5 3 7 3 0 4 17
6 52 3 0 30 21 0

Step 7: Go to step 3 and repeat the procedure until you arrive at an optimal assignments.

Step 8: Determine an assignment

    Depots
    7 8 9 10 11 12
From 1 16 40 4 27 0 26
2 0 0 17 43 59 28
3 0 5 23 24 5 5
4 7 5 0 14 0 5
5 3 7 3 0 4 17
6 52 3 0 30 21 0

Here all the six assignments have been made.

The optimal assignment schedule and total distance is

From To Total Distance
1 11 15
2 8 19
3 7 17
4 9 38
5 10 16
6 12 20
Total 125

∴The optimum Distance (minimum) = 125 kms

shaalaa.com
  Is there an error in this question or solution?
Chapter 10: Operations Research - Miscellaneous problems [Page 262]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 12 TN Board
Chapter 10 Operations Research
Miscellaneous problems | Q 6 | Page 262

RELATED QUESTIONS

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:

         Jobs

 

 

                          Machines

P

Q

R

S

                Processing Cost (Rs.)

 

A

31

25

33

29

B

25

24

23

21

C

19

21

23

24

D

38

36

34

40

 How should the jobs be assigned to the four machines so that the total processing cost is minimum?


Solve the following minimal assignment problem and hence find minimum time where  '- ' indicates that job cannot be assigned to the machine : 

Machines Processing time in hours
A B C D E
M1 9 11 15 10 11
M2 12 9 - 10 9
M3 - 11 14 11 7
M4 14 8 12 7 8

Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:

Job Machines (Profit in ₹)
A B C D E
1 30 37 40 28 40
2 40 24 27 21 36
3 40 32 33 30 35
4 25 38 40 36 36
5 29 62 41 34 39

Find the optimal assignment schedule.


The assignment problem is said to be unbalance if ______


Fill in the blank :

When an assignment problem has more than one solution, then it is _______ optimal solution.


A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.

  Programmers
    P Q R
Programmers 1 120 100 80
  2 80 90 110
  3 110 140 120

Assign the programmers to the programme in such a way that the total computer time is least.


Choose the correct alternative:

If number of sources is not equal to number of destinations, the assignment problem is called ______


Choose the correct alternative:

The solution for an assignment problem is optimal if


Choose the correct alternative:

In an assignment problem involving four workers and three jobs, total number of assignments possible are


A department store has four workers to pack goods. The times (in minutes) required for each worker to complete the packings per item sold is given below. How should the manager of the store assign the jobs to the workers, so as to minimize the total time of packing?

Workers Packing of
  Books Toys Crockery Cutlery
A 3 11 10 8
B 13 2 12 12
C 3 4 6 1
D 4 15 4 9

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×