Advertisements
Advertisements
Question
Choose the correct alternative:
Number of basic allocation in any row or column in an assignment problem can be
Options
exactly one
at least one
at most one
none of these
Advertisements
Solution
exactly one
APPEARS IN
RELATED QUESTIONS
Solve the following minimal assignment problem and hence find the minimum value :
| I | II | III | IV | |
| A | 2 | 10 | 9 | 7 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:
| Job | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 30 | 37 | 40 | 28 | 40 |
| 2 | 40 | 24 | 27 | 21 | 36 |
| 3 | 40 | 32 | 33 | 30 | 35 |
| 4 | 25 | 38 | 40 | 36 | 36 |
| 5 | 29 | 62 | 41 | 34 | 39 |
Find the optimal assignment schedule.
The assignment problem is said to be balanced if ______.
Fill in the blank :
An _______ is a special type of linear programming problem.
Choose the correct alternative:
The assignment problem is said to be balanced if ______
In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added
Give mathematical form of Assignment problem
A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:
| Tasks | |||||
| 1 | 2 | 3 | 4 | ||
| Subordinates | P | 8 | 26 | 17 | 11 |
| Q | 13 | 28 | 4 | 26 | |
| R | 38 | 19 | 18 | 15 | |
| S | 9 | 26 | 24 | 10 | |
How should the tasks be allocated to subordinates so as to minimize the total manhours?
A car hire company has one car at each of five depots a, b, c, d and e. A customer in each of the fine towers A, B, C, D and E requires a car. The distance (in miles) between the depots (origins) and the towers(destinations) where the customers are given in the following distance matrix.
| a | b | c | d | e | |
| A | 160 | 130 | 175 | 190 | 200 |
| B | 135 | 120 | 130 | 160 | 175 |
| C | 140 | 110 | 155 | 170 | 185 |
| D | 50 | 50 | 80 | 80 | 110 |
| E | 55 | 35 | 70 | 80 | 105 |
How should the cars be assigned to the customers so as to minimize the distance travelled?
A job production unit has four jobs P, Q, R, S which can be manufactured on each of the four machines I, II, III and IV. The processing cost of each job for each machine is given in the following table :
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 31 | 25 | 33 | 29 |
| Q | 25 | 24 | 23 | 21 |
| R | 19 | 21 | 23 | 24 |
| S | 38 | 36 | 34 | 40 |
Complete the following activity to find the optimal assignment to minimize the total processing cost.
Solution:
Step 1: Subtract the smallest element in each row from every element of it. New assignment matrix is obtained as follows :
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 6 | 0 | 8 | 4 |
| Q | 4 | 3 | 2 | 0 |
| R | 0 | 2 | 4 | 5 |
| S | 4 | 2 | 0 | 6 |
Step 2: Subtract the smallest element in each column from every element of it. New assignment matrix is obtained as above, because each column in it contains one zero.
Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros:
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 6 | 0 | 8 | 4 |
| Q | 4 | 3 | 2 | 0 |
| R | 0 | 2 | 4 | 5 |
| S | 4 | 2 | 0 | 6 |
Step 4: From step 3, as the minimum number of straight lines required to cover all zeros in the assignment matrix equals the number of rows/columns. Optimal solution has reached.
Examine the rows one by one starting with the first row with exactly one zero is found. Mark the zero by enclosing it in (`square`), indicating assignment of the job. Cross all the zeros in the same column. This step is shown in the following table :
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 6 | 0 | 8 | 4 |
| Q | 4 | 3 | 2 | 0 |
| R | 0 | 2 | 4 | 5 |
| S | 4 | 2 | 0 | 6 |
Step 5: It is observed that all the zeros are assigned and each row and each column contains exactly one assignment. Hence, the optimal (minimum) assignment schedule is :
| Job | Machine | Min.cost |
| P | II | `square` |
| Q | `square` | 21 |
| R | I | `square` |
| S | III | 34 |
Hence, total (minimum) processing cost = 25 + 21 + 19 + 34 = ₹`square`
