Advertisements
Advertisements
प्रश्न
Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 3 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
Advertisements
उत्तर
Step 1: Row minimum
Subtract the smallest element in each row from every element in its row.
∴ The matrix obtained is given below:
| I | II | III | IV | V | |
| 1 | 5 | 0 | 4 | 13 | 6 |
| 2 | 7 | 3 | 0 | 6 | 8 |
| 3 | 1 | 0 | 2 | 2 | 3 |
| 4 | 9 | 0 | 3 | 8 | 6 |
| 5 | 5 | 0 | 8 | 13 | 4 |
Step 2: Column minimum
Subtract the smallest element in each column of assignment matrix obtained in step 1 from every element in its column.
| I | II | III | IV | V | |
| 1 | 4 | 0 | 4 | 11 | 3 |
| 2 | 6 | 3 | 0 | 4 | 5 |
| 3 | 0 | 0 | 2 | 0 | 0 |
| 4 | 8 | 0 | 3 | 6 | 3 |
| 5 | 4 | 0 | 8 | 11 | 1 |
Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros.
First cover all rows and columns which have maximum number of zeros.
| I | II | III | IV | V | |
| 1 | 4 | `cancel0` | 4 | 11 | 3 |
| 2 | `cancel6` | `cancel3` | `cancel0` | `cancel4` | `cancel5` |
| 3 | `cancel0` | `cancel0` | `cancel2` | `cancel0` | `cancel0` |
| 4 | 8 | `cancel0` | 3 | 6 | 3 |
| 5 | 4 | `cancel0` | 8 | 11 | 1 |
Step 4: From step 3, minimum number of lines covering all the zeros are 3, which is less than order of matrix, i.e., 5.
∴ Select smallest element from all the uncovered elements, i.e., 1 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
| I | II | III | IV | V | |
| 1 | 3 | 0 | 3 | 10 | 2 |
| 2 | 6 | 4 | 0 | 4 | 5 |
| 3 | 0 | 1 | 2 | 0 | 0 |
| 4 | 7 | 0 | 2 | 5 | 2 |
| 5 | 3 | 0 | 7 | 10 | 0 |
Step 5: Draw minimum number of vertical and horizontal lines to cover all zeros.
| I | II | III | IV | V | |
| 1 | 3 | `cancel0` | 3 | 10 | 2 |
| 2 | `cancel6` | `cancel4` | `cancel0` | `cancel4` | `cancel5` |
| 3 | `cancel0` | `cancel1` | `cancel2` | `cancel0` | `cancel0` |
| 4 | 7 | `cancel0` | 2 | 5 | 2 |
| 5 | `cancel3` | `cancel0` | `cancel7` | `cancel10` | `cancel0` |
Step 6: From step 5, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e., 5.
∴ Select smallest element from all the uncovered elements, i.e., 2 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
| I | II | III | IV | V | |
| 1 | 1 | 0 | 1 | 8 | 0 |
| 2 | 6 | 6 | 0 | 4 | 5 |
| 3 | 0 | 3 | 2 | 0 | 0 |
| 4 | 5 | 0 | 0 | 3 | 0 |
| 5 | 3 | 2 | 7 | 10 | 0 |
Step 7: Draw minimum number of vertical and horizontal lines to cover all zeros.
| I | II | III | IV | V | |
| 1 | 1 | `cancel0` | `cancel1` | 8 | `cancel0` |
| 2 | 6 | `cancel6` | `cancel0` | 4 | `cancel5` |
| 3 | `cancel0` | `cancel3` | `cancel2` | `cancel0` | `cancel0` |
| 4 | 5 | `cancel0` | `cancel0` | 3 | `cancel0` |
| 5 | 3 | `cancel2` | `cancel7` | 10 | `cancel0` |
Step 8: From step 7, minimum number of lines covering all the zeros are 4, which is less than order of matrix, i.e.,5.
∴ Select smallest element from all the uncovered elements, i.e., 1 and subtract it from all the uncovered elements and add it to the elements which lie at the intersection of two lines.
| I | II | III | IV | V | |
| 1 | 0 | 0 | 1 | 7 | 0 |
| 2 | 5 | 6 | 0 | 3 | 5 |
| 3 | 0 | 4 | 3 | 0 | 1 |
| 4 | 4 | 0 | 0 | 2 | 0 |
| 5 | 2 | 2 | 7 | 9 | 0 |
Step 9: Draw minimum number of vertical and horizontal lines to cover all zeros.
| I | II | III | IV | V | |
| 1 | `cancel0` | `cancel0` | `cancel1` | `cancel7` | `cancel0` |
| 2 | 5 | 6 | `cancel0` | 3 | `cancel5` |
| 3 | `cancel0` | `cancel4` | `cancel3` | `cancel0` | `cancel1` |
| 4 | `cancel4` | `cancel0` | `cancel0` | `cancel2` | `cancel0` |
| 5 | 2 | 2 | `cancel7` | 9 | `cancel0` |
Step 10: From step 9, minimum number of lines covering all the zeros are 5, which is equal to order of the matrix, i.e., 5.
∴ Select a row with exactly one zero, enclose that zero in ( ) and cross out all zeros in its respective column.
Similarly, examine each row and column and mark the assignment ( ).
∴ The matrix obtained is as follows:
| I | II | III | IV | V | |
| 1 | 0 | `cancel0` | 1 | 7 | `cancel0` |
| 2 | 5 | 6 | 0 | 3 | 5 |
| 3 | `cancel0` | 4 | 3 | 0 | 1 |
| 4 | 4 | 0 | `cancel0` | 2 | `cancel0` |
| 5 | 2 | 2 | 7 | 9 | 0 |
Step 11: The matrix obtained in step 10 contains exactly one assignment for each row and column.
∴ Optimal assignment schedule is as follows:
| Jobs | Wagons | Mileage |
| 1 | I | 10 |
| 2 | II | 6 |
| 3 | III | 4 |
| 4 | IV | 9 |
| 5 | V | 10 |
∴ Total minimum mileage = 10 + 6 = 4 + 9 + 10 = 39.
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
|
Jobs
|
Machines |
|||
|
P |
Q |
R |
S |
|
|
Processing Cost (Rs.)
|
||||
|
A |
31 |
25 |
33 |
29 |
|
B |
25 |
24 |
23 |
21 |
|
C |
19 |
21 |
23 |
24 |
|
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
Service Time ( in hrs.)
| Counters | Salesmen | |||
| A | B | C | D | |
| W | 41 | 72 | 39 | 52 |
| X | 22 | 29 | 49 | 65 |
| Y | 27 | 39 | 60 | 51 |
| Z | 45 | 50 | 48 | 52 |
Solve the following minimal assignment problem :
| Machines | A | B | C | D | E |
| M1 | 27 | 18 | ∞ | 20 | 21 |
| M2 | 31 | 24 | 21 | 12 | 17 |
| M3 | 20 | 17 | 20 | ∞ | 16 |
| M4 | 21 | 28 | 20 | 16 | 27 |
Solve the following maximal assignment problem :
| Branch Manager | Monthly Business ( Rs. lakh) | |||
| A | B | C | D | |
| P | 11 | 11 | 9 | 9 |
| Q | 13 | 16 | 11 | 10 |
| R | 12 | 17 | 13 | 8 |
| S | 16 | 14 | 16 | 12 |
Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:
| Job | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 30 | 37 | 40 | 28 | 40 |
| 2 | 40 | 24 | 27 | 21 | 36 |
| 3 | 40 | 32 | 33 | 30 | 35 |
| 4 | 25 | 38 | 40 | 36 | 36 |
| 5 | 29 | 62 | 41 | 34 | 39 |
Find the optimal assignment schedule.
The assignment problem is said to be unbalance if ______
The objective of an assignment problem is to assign ______.
Fill in the blank :
When an assignment problem has more than one solution, then it is _______ optimal solution.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
Choose the correct alternative:
The assignment problem is generally defined as a problem of ______
Choose the correct alternative:
Assignment Problem is special case of ______
Choose the correct alternative:
When an assignment problem has more than one solution, then it is ______
In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added
State whether the following statement is True or False:
In assignment problem each worker or machine is assigned only one job
What is the Assignment problem?
What is the difference between Assignment Problem and Transportation Problem?
Three jobs A, B and C one to be assigned to three machines U, V and W. The processing cost for each job machine combination is shown in the matrix given below. Determine the allocation that minimizes the overall processing cost.
| Machine | ||||
| U | V | W | ||
| Jobs | A | 17 | 25 | 31 |
| B | 10 | 25 | 16 | |
| C | 12 | 14 | 11 | |
(cost is in ₹ per unit)
Find the optimal solution for the assignment problem with the following cost matrix.
| Area | |||||
| 1 | 2 | 3 | 4 | ||
| P | 11 | 17 | 8 | 16 | |
| Salesman | Q | 9 | 7 | 12 | 6 |
| R | 13 | 16 | 15 | 12 | |
| S | 14 | 10 | 12 | 11 | |
Assign four trucks 1, 2, 3 and 4 to vacant spaces A, B, C, D, E and F so that distance travelled is minimized. The matrix below shows the distance.
| 1 | 2 | 3 | 4 | |
| A | 4 | 7 | 3 | 7 |
| B | 8 | 2 | 5 | 5 |
| C | 4 | 9 | 6 | 9 |
| D | 7 | 5 | 4 | 8 |
| E | 6 | 3 | 5 | 4 |
| F | 6 | 8 | 7 | 3 |
Choose the correct alternative:
The solution for an assignment problem is optimal if
Choose the correct alternative:
In an assignment problem involving four workers and three jobs, total number of assignments possible are
A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:
| To | |||||||
| 7 | 8 | 9 | 10 | 11 | 12 | ||
| From | 1 | 31 | 62 | 29 | 42 | 15 | 41 |
| 2 | 12 | 19 | 39 | 55 | 71 | 40 | |
| 3 | 17 | 29 | 50 | 41 | 22 | 22 | |
| 4 | 35 | 40 | 38 | 42 | 27 | 33 | |
| 5 | 19 | 30 | 29 | 16 | 20 | 33 | |
| 6 | 72 | 30 | 30 | 50 | 41 | 20 | |
How should the truck be dispersed so as to minimize the total distance travelled?
Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 7 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
A job production unit has four jobs P, Q, R, S which can be manufactured on each of the four machines I, II, III and IV. The processing cost of each job for each machine is given in the following table :
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 31 | 25 | 33 | 29 |
| Q | 25 | 24 | 23 | 21 |
| R | 19 | 21 | 23 | 24 |
| S | 38 | 36 | 34 | 40 |
Complete the following activity to find the optimal assignment to minimize the total processing cost.
Solution:
Step 1: Subtract the smallest element in each row from every element of it. New assignment matrix is obtained as follows :
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 6 | 0 | 8 | 4 |
| Q | 4 | 3 | 2 | 0 |
| R | 0 | 2 | 4 | 5 |
| S | 4 | 2 | 0 | 6 |
Step 2: Subtract the smallest element in each column from every element of it. New assignment matrix is obtained as above, because each column in it contains one zero.
Step 3: Draw minimum number of vertical and horizontal lines to cover all zeros:
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 6 | 0 | 8 | 4 |
| Q | 4 | 3 | 2 | 0 |
| R | 0 | 2 | 4 | 5 |
| S | 4 | 2 | 0 | 6 |
Step 4: From step 3, as the minimum number of straight lines required to cover all zeros in the assignment matrix equals the number of rows/columns. Optimal solution has reached.
Examine the rows one by one starting with the first row with exactly one zero is found. Mark the zero by enclosing it in (`square`), indicating assignment of the job. Cross all the zeros in the same column. This step is shown in the following table :
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 6 | 0 | 8 | 4 |
| Q | 4 | 3 | 2 | 0 |
| R | 0 | 2 | 4 | 5 |
| S | 4 | 2 | 0 | 6 |
Step 5: It is observed that all the zeros are assigned and each row and each column contains exactly one assignment. Hence, the optimal (minimum) assignment schedule is :
| Job | Machine | Min.cost |
| P | II | `square` |
| Q | `square` | 21 |
| R | I | `square` |
| S | III | 34 |
Hence, total (minimum) processing cost = 25 + 21 + 19 + 34 = ₹`square`
