Advertisements
Advertisements
प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:
| Jobs | Machines (Processing Cost in ₹) |
|||
| P | Q | R | S | |
| A | 31 | 25 | 33 | 29 |
| B | 25 | 24 | 23 | 21 |
| C | 19 | 21 | 23 | 24 |
| D | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
Advertisements
उत्तर
Step 1: Row minimum
Subtract the smallest element in each row from every element in its row. The matrix obtained is given below:
| Jobs | Machines (Processing Cost in ₹) |
|||
| P | Q | R | S | |
| A | 6 | 0 | 8 | 4 |
| B | 4 | 3 | 2 | 0 |
| C | 0 | 2 | 4 | 5 |
| D | 4 | 2 | 0 | 6 |
Step 2: Column minimum
Subtract the smallest element in each column of assignment matrix obtained in step 1 from every element in its column.
| Jobs | Machine (Processing Cost in ₹) |
|||
| P | Q | R | S | |
| A | 6 | 0 | 8 | 4 |
| B | 4 | 3 | 2 | 0 |
| C | 0 | 2 | 4 | 5 |
| D | 4 | 2 | 0 | 6 |
Step 3:
Draw minimum number of vertical and horizontal lines to cover all zeros.
First cover all rows and columns which have maximum number of zeros.
| Jons | Machines (Processing Cost in ₹) |
|||
| P | Q | R | S | |
| A | 6 | 0 | 8 | 4 |
| B | 4 | 3 | 2 | 0 |
| C | 0 | 2 | 4 | 5 |
| D | 4 | 2 | 0 | 6 |
Step 4:
From step 3, minimum number of lines covering all the zeros are 4, which is equal to order of the matrix, i.e., 4
∴ Select a row with exactly one zero, enclose that zero in () and cross out all zeros in its respective column.
Similarly, examine each row and column and mark the assignment ().
∴ The matrix obtained is as follows:
| Jobs | Machines (Processing Cost in ₹) |
|||
| P | Q | R | S | |
| A | 6 | 0 | 8 | 4 |
| B | 4 | 3 | 2 | 0 |
| C | 0 | 2 | 4 | 5 |
| D | 4 | 2 | 0 | 6 |
Step 5:
The matrix obtained in step 4 contains exactly one assignment for each row and column.
∴ Optimal assignment schedule is as follows:
| Jobs | Machines | Processing cost (₹) |
| A | Q | 25 |
| B | S | 21 |
| C | P | 19 |
| D | R | 34 |
∴ Total minimum processing cost = 25 + 21 + 19 + 34 = ₹ 99.
APPEARS IN
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:
|
Jobs
|
Machines |
|||
|
P |
Q |
R |
S |
|
|
Processing Cost (Rs.)
|
||||
|
A |
31 |
25 |
33 |
29 |
|
B |
25 |
24 |
23 |
21 |
|
C |
19 |
21 |
23 |
24 |
|
D |
38 |
36 |
34 |
40 |
How should the jobs be assigned to the four machines so that the total processing cost is minimum?
Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
Service Time ( in hrs.)
| Counters | Salesmen | |||
| A | B | C | D | |
| W | 41 | 72 | 39 | 52 |
| X | 22 | 29 | 49 | 65 |
| Y | 27 | 39 | 60 | 51 |
| Z | 45 | 50 | 48 | 52 |
Solve the following minimal assignment problem :
| Machines | A | B | C | D | E |
| M1 | 27 | 18 | ∞ | 20 | 21 |
| M2 | 31 | 24 | 21 | 12 | 17 |
| M3 | 20 | 17 | 20 | ∞ | 16 |
| M4 | 21 | 28 | 20 | 16 | 27 |
Determine `l_92 and l_93, "given that" l_91 = 97, d_91 = 38 and q_92 = 27/59`
Solve the following minimal assignment problem and hence find minimum time where '- ' indicates that job cannot be assigned to the machine :
| Machines | Processing time in hours | ||||
| A | B | C | D | E | |
| M1 | 9 | 11 | 15 | 10 | 11 |
| M2 | 12 | 9 | - | 10 | 9 |
| M3 | - | 11 | 14 | 11 | 7 |
| M4 | 14 | 8 | 12 | 7 | 8 |
Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:
| Job | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 30 | 37 | 40 | 28 | 40 |
| 2 | 40 | 24 | 27 | 21 | 36 |
| 3 | 40 | 32 | 33 | 30 | 35 |
| 4 | 25 | 38 | 40 | 36 | 36 |
| 5 | 29 | 62 | 41 | 34 | 39 |
Find the optimal assignment schedule.
The assignment problem is said to be balanced if ______.
Choose the correct alternative :
The assignment problem is said to be balanced if it is a ______.
Choose the correct alternative :
In an assignment problem if number of rows is greater than number of columns then
In an assignment problem, if number of column is greater than number of rows, then a dummy column is added.
State whether the following is True or False :
In assignment problem, each facility is capable of performing each task.
Solve the following problem :
A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.
| I | II | III | IV | |
| A | 7 | 25 | 26 | 10 |
| B | 12 | 27 | 3 | 25 |
| C | 37 | 18 | 17 | 14 |
| D | 18 | 25 | 23 | 9 |
How should the tasks be allocated, one to a man, as to minimize the total man hours?
Solve the following problem :
A dairy plant has five milk tankers, I, II, III, IV and V. These milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
| I | II | III | IV | V | |
| A | 150 | 120 | 175 | 180 | 200 |
| B | 125 | 110 | 120 | 150 | 165 |
| C | 130 | 100 | 145 | 160 | 175 |
| D | 40 | 40 | 70 | 70 | 100 |
| E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
Choose the correct alternative:
Assignment Problem is special case of ______
Choose the correct alternative:
The assignment problem is said to be balanced if ______
If the given matrix is ______ matrix, the assignment problem is called balanced problem
What is the Assignment problem?
Assign four trucks 1, 2, 3 and 4 to vacant spaces A, B, C, D, E and F so that distance travelled is minimized. The matrix below shows the distance.
| 1 | 2 | 3 | 4 | |
| A | 4 | 7 | 3 | 7 |
| B | 8 | 2 | 5 | 5 |
| C | 4 | 9 | 6 | 9 |
| D | 7 | 5 | 4 | 8 |
| E | 6 | 3 | 5 | 4 |
| F | 6 | 8 | 7 | 3 |
Choose the correct alternative:
The purpose of a dummy row or column in an assignment problem is to
A car hire company has one car at each of five depots a, b, c, d and e. A customer in each of the fine towers A, B, C, D and E requires a car. The distance (in miles) between the depots (origins) and the towers(destinations) where the customers are given in the following distance matrix.
| a | b | c | d | e | |
| A | 160 | 130 | 175 | 190 | 200 |
| B | 135 | 120 | 130 | 160 | 175 |
| C | 140 | 110 | 155 | 170 | 185 |
| D | 50 | 50 | 80 | 80 | 110 |
| E | 55 | 35 | 70 | 80 | 105 |
How should the cars be assigned to the customers so as to minimize the distance travelled?
A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.
| I | II | III | IV | V | |
| A | 150 | 120 | 175 | 180 | 200 |
| B | 125 | 110 | 120 | 150 | 165 |
| C | 130 | 100 | 145 | 160 | 170 |
| D | 40 | 40 | 70 | 70 | 100 |
| E | 45 | 25 | 60 | 70 | 95 |
How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?
A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:
| Job | Machines (Processing cost in ₹) |
|||
| I | II | III | IV | |
| P | 31 | 25 | 33 | 29 |
| Q | 25 | 24 | 23 | 21 |
| R | 19 | 21 | 23 | 24 |
| S | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 7 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:
| I | II | III | IV | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Complete the following activity to allocate tasks to subordinates to minimize total time.
Solution:
Step I: Subtract the smallest element of each row from every element of that row:
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Step II: Since all column minimums are zero, no need to subtract anything from columns.
Step III: Draw the minimum number of lines to cover all zeros.
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Since minimum number of lines = order of matrix, optimal solution has been reached
Optimal assignment is A →`square` B →`square`
C →IV D →`square`
Total minimum time = `square` hours.
