मराठी
महाराष्ट्र राज्य शिक्षण मंडळएचएससी वाणिज्य (इंग्रजी माध्यम) इयत्ता १२ वी

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table: - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:

Jobs Machines
(Processing Cost in ₹)
P Q R S
A 31 25 33 29
B 25 24 23 21
C 19 21 23 24
D 38 36 34 40

Find the optimal assignment to minimize the total processing cost.

बेरीज
Advertisements

उत्तर

Step 1: Row minimum
Subtract the smallest element in each row from every element in its row. The matrix obtained is given below:

Jobs Machines
(Processing Cost in ₹)
P Q R S
A 6 0 8 4
B 4 3 2 0
C 0 2 4 5
D 4 2 0 6

Step 2: Column minimum
Subtract the smallest element in each column of assignment matrix obtained in step 1 from every element in its column.

Jobs Machine
(Processing Cost in ₹)
P Q R S
A 6 0 8 4
B 4 3 2 0
C 0 2 4 5
D 4 2 0 6

Step 3:
Draw minimum number of vertical and horizontal lines to cover all zeros.
First cover all rows and columns which have maximum number of zeros.

Jons Machines
(Processing Cost in ₹)
P Q R S
A 6 0 8 4
B 4 3 2 0
C 0 2 4 5
D 4 2 0 6

Step 4:
From step 3, minimum number of lines covering all the zeros are 4, which is equal to order of the matrix, i.e., 4
∴ Select a row with exactly one zero, enclose that zero in () and cross out all zeros in its respective column.
Similarly, examine each row and column and mark the assignment ().
∴ The matrix obtained is as follows:

Jobs Machines
(Processing Cost in ₹)
P Q R S
A 6 0 8 4
B 4 3 2 0
C 0 2 4 5
D 4 2 0 6

Step 5:
The matrix obtained in step 4 contains exactly one assignment for each row and column.
∴ Optimal assignment schedule is as follows:

Jobs Machines Processing cost (₹)
A Q 25
B S 21
C P 19
D R 34

∴ Total minimum processing cost = 25 + 21 + 19 + 34 = ₹ 99.

shaalaa.com
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 7: Assignment Problem and Sequencing - Exercise 7.1 [पृष्ठ ११८]

APPEARS IN

बालभारती Mathematics and Statistics 2 (Commerce) [English] Standard 12 Maharashtra State Board
पाठ 7 Assignment Problem and Sequencing
Exercise 7.1 | Q 1 | पृष्ठ ११८

व्हिडिओ ट्यूटोरियलVIEW ALL [1]

संबंधित प्रश्‍न

Solve the following minimal assignment problem and hence find minimum time where  '- ' indicates that job cannot be assigned to the machine : 

Machines Processing time in hours
A B C D E
M1 9 11 15 10 11
M2 12 9 - 10 9
M3 - 11 14 11 7
M4 14 8 12 7 8

Solve the following maximal assignment problem :

Branch Manager Monthly Business ( Rs. lakh)
A B C D
P 11 11 9 9
Q 13 16 11 10
R 12 17 13 8
S 16 14 16 12

 


Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?

  I II III IV V
1 10 5 9 18 11
2 13 9 6 12 14
3 3 2 4 4 5
4 18 9 12 17 15
5 11 6 14 19 10

Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:

Job Machines (Profit in ₹)
A B C D E
1 30 37 40 28 40
2 40 24 27 21 36
3 40 32 33 30 35
4 25 38 40 36 36
5 29 62 41 34 39

Find the optimal assignment schedule.


The assignment problem is said to be unbalance if ______


The assignment problem is said to be balanced if ______.


Choose the correct alternative :

The assignment problem is said to be balanced if it is a ______.


The objective of an assignment problem is to assign ______. 


Fill in the blank :

An _______ is a special type of linear programming problem.


In an assignment problem, if number of column is greater than number of rows, then a dummy column is added.


State whether the following is True or False :

It is not necessary to express an assignment problem into n x n matrix.


Solve the following problem :

A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.

  I II III IV
A 7 25 26 10
B 12 27 3 25
C 37 18 17 14
D 18 25 23 9

How should the tasks be allocated, one to a man, as to minimize the total man hours?


Choose the correct alternative:

When an assignment problem has more than one solution, then it is ______


State whether the following statement is True or False:

The objective of an assignment problem is to assign number of jobs to equal number of persons at maximum cost


What is the Assignment problem?


Give mathematical form of Assignment problem


Three jobs A, B and C one to be assigned to three machines U, V and W. The processing cost for each job machine combination is shown in the matrix given below. Determine the allocation that minimizes the overall processing cost.

    Machine
    U V W
Jobs A 17 25 31
B 10 25 16
C 12 14 11

(cost is in ₹ per unit)


A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.

  Programmers
    P Q R
Programmers 1 120 100 80
  2 80 90 110
  3 110 140 120

Assign the programmers to the programme in such a way that the total computer time is least.


A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:

    Tasks
    1 2 3 4
Subordinates P 8 26 17 11
  Q 13 28 4 26
  R 38 19 18 15
  S 9 26 24 10

How should the tasks be allocated to subordinates so as to minimize the total manhours?


Find the optimal solution for the assignment problem with the following cost matrix.

    Area
    1 2 3 4
  P 11 17 8 16
Salesman Q 9 7 12 6
  R 13 16 15 12
  S 14 10 12 11

Choose the correct alternative:

North – West Corner refers to ______


Choose the correct alternative:

If number of sources is not equal to number of destinations, the assignment problem is called ______


Choose the correct alternative:

The solution for an assignment problem is optimal if


Choose the correct alternative:

In an assignment problem involving four workers and three jobs, total number of assignments possible are


A dairy plant has five milk tankers, I, II, III, IV and V. Three milk tankers are to be used on five delivery routes A, B, C, D and E. The distances (in kms) between the dairy plant and the delivery routes are given in the following distance matrix.

  I II III IV V
A 150 120 175 180 200
B 125 110 120 150 165
C 130 100 145 160 170
D 40 40 70 70 100
E 45 25 60 70 95

How should the milk tankers be assigned to the chilling center so as to minimize the distance travelled?


A job production unit has four jobs P, Q, R, and S which can be manufactured on each of the four machines I, II, III, and IV. The processing cost of each job for each machine is given in the following table:

Job Machines
(Processing cost in ₹)
I II III IV
P 31 25 33 29
Q 25 24 23 21
R 19 21 23 24
S 38 36 34 40

Find the optimal assignment to minimize the total processing cost.


A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:

  I II III IV
A 3 11 10 8
B 13 2 12 2
C 3 4 6 1
D 4 15 4 9

Complete the following activity to allocate tasks to subordinates to minimize total time.

Solution:

Step I: Subtract the smallest element of each row from every element of that row:

  I II III IV
A 0 8 7 5
B 11 0 10 0
C 2 3 5 0
D 0 11 0 5

Step II: Since all column minimums are zero, no need to subtract anything from columns.

Step III: Draw the minimum number of lines to cover all zeros.

  I II III IV
A 0 8 7 5
B 11 0 10 0
C 2 3 5 0
D 0 11 0 5

Since minimum number of lines = order of matrix, optimal solution has been reached

Optimal assignment is A →`square`  B →`square`

C →IV  D →`square`

Total minimum time = `square` hours.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×