Advertisements
Advertisements
प्रश्न
A departmental head has three jobs and four subordinates. The subordinates differ in their capabilities and the jobs differ in their work
contents. With the help of the performance matrix given below, find out which of the four subordinates should be assigned which jobs ?
| Subordinates | Jobs | ||
| I | II | III | |
| A | 7 | 3 | 5 |
| B | 2 | 7 | 4 |
| C | 6 | 5 | 3 |
| D | 3 | 4 | 7 |
Advertisements
उत्तर
As the problem is unbalanced a dummy · job IV is introduced with zero performance as, the for:
| I | II | III | IV | |
| A | 7 | 3 | 5 | 0 |
| B | 2 | 7 | 4 | 0 |
| C | 6 | 5 | 3 | 0 |
| D | 3 | 4 | 7 | 0 |
As minimum element of each row is 'O' hence minimum element of each column is subtracted from all the elements of that column,
| I | II | III | IV | |
| A | 5 | 0 | 2 | 0 |
| B | 0 | 4 | 1 | 0 |
| C | 4 | 2 | 0 | 0 |
| D | 1 | 1 | 4 | 0 |
All the zeros of the above matrix a re covered with minimum number of lines is as below :
As the number of lines covering zeros is equal to the number of rows and columns. hence the optional solution is obtained it is as shown below :

As D gets a dummy job N, hence the assignment is as shown below :
A → Job II
B → Job I
C → Job III
and performance is 3 + 2 + 3 = 8 units
APPEARS IN
संबंधित प्रश्न
Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
Service Time ( in hrs.)
| Counters | Salesmen | |||
| A | B | C | D | |
| W | 41 | 72 | 39 | 52 |
| X | 22 | 29 | 49 | 65 |
| Y | 27 | 39 | 60 | 51 |
| Z | 45 | 50 | 48 | 52 |
Solve the following minimal assignment problem :
| Machines | A | B | C | D | E |
| M1 | 27 | 18 | ∞ | 20 | 21 |
| M2 | 31 | 24 | 21 | 12 | 17 |
| M3 | 20 | 17 | 20 | ∞ | 16 |
| M4 | 21 | 28 | 20 | 16 | 27 |
Determine `l_92 and l_93, "given that" l_91 = 97, d_91 = 38 and q_92 = 27/59`
Solve the following maximal assignment problem :
| Branch Manager | Monthly Business ( Rs. lakh) | |||
| A | B | C | D | |
| P | 11 | 11 | 9 | 9 |
| Q | 13 | 16 | 11 | 10 |
| R | 12 | 17 | 13 | 8 |
| S | 16 | 14 | 16 | 12 |
Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:
| Job | Machines (Profit in ₹) | ||||
| A | B | C | D | E | |
| 1 | 30 | 37 | 40 | 28 | 40 |
| 2 | 40 | 24 | 27 | 21 | 36 |
| 3 | 40 | 32 | 33 | 30 | 35 |
| 4 | 25 | 38 | 40 | 36 | 36 |
| 5 | 29 | 62 | 41 | 34 | 39 |
Find the optimal assignment schedule.
The assignment problem is said to be unbalance if ______
The assignment problem is said to be balanced if ______.
Choose the correct alternative :
The assignment problem is said to be balanced if it is a ______.
The objective of an assignment problem is to assign ______.
Fill in the blank :
When an assignment problem has more than one solution, then it is _______ optimal solution.
Fill in the blank :
An _______ is a special type of linear programming problem.
Solve the following problem :
A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.
| I | II | III | IV | |
| A | 7 | 25 | 26 | 10 |
| B | 12 | 27 | 3 | 25 |
| C | 37 | 18 | 17 | 14 |
| D | 18 | 25 | 23 | 9 |
How should the tasks be allocated, one to a man, as to minimize the total man hours?
Choose the correct alternative:
Assignment Problem is special case of ______
State whether the following statement is True or False:
The objective of an assignment problem is to assign number of jobs to equal number of persons at maximum cost
A computer centre has got three expert programmers. The centre needs three application programmes to be developed. The head of the computer centre, after studying carefully the programmes to be developed, estimates the computer time in minitues required by the experts to the application programme as follows.
| Programmers | ||||
| P | Q | R | ||
| Programmers | 1 | 120 | 100 | 80 |
| 2 | 80 | 90 | 110 | |
| 3 | 110 | 140 | 120 | |
Assign the programmers to the programme in such a way that the total computer time is least.
Assign four trucks 1, 2, 3 and 4 to vacant spaces A, B, C, D, E and F so that distance travelled is minimized. The matrix below shows the distance.
| 1 | 2 | 3 | 4 | |
| A | 4 | 7 | 3 | 7 |
| B | 8 | 2 | 5 | 5 |
| C | 4 | 9 | 6 | 9 |
| D | 7 | 5 | 4 | 8 |
| E | 6 | 3 | 5 | 4 |
| F | 6 | 8 | 7 | 3 |
Choose the correct alternative:
The solution for an assignment problem is optimal if
Five wagons are available at stations 1, 2, 3, 4 and 5. These are required at 5 stations I, II, III, IV and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 7 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
A plant manager has four subordinates and four tasks to perform. The subordinates differ in efficiency and task differ in their intrinsic difficulty. Estimates of the time subordinate would take to perform tasks are given in the following table:
| I | II | III | IV | |
| A | 3 | 11 | 10 | 8 |
| B | 13 | 2 | 12 | 2 |
| C | 3 | 4 | 6 | 1 |
| D | 4 | 15 | 4 | 9 |
Complete the following activity to allocate tasks to subordinates to minimize total time.
Solution:
Step I: Subtract the smallest element of each row from every element of that row:
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Step II: Since all column minimums are zero, no need to subtract anything from columns.
Step III: Draw the minimum number of lines to cover all zeros.
| I | II | III | IV | |
| A | 0 | 8 | 7 | 5 |
| B | 11 | 0 | 10 | 0 |
| C | 2 | 3 | 5 | 0 |
| D | 0 | 11 | 0 | 5 |
Since minimum number of lines = order of matrix, optimal solution has been reached
Optimal assignment is A →`square` B →`square`
C →IV D →`square`
Total minimum time = `square` hours.
