Advertisements
Advertisements
प्रश्न
Find the optimal solution for the assignment problem with the following cost matrix.
| Area | |||||
| 1 | 2 | 3 | 4 | ||
| P | 11 | 17 | 8 | 16 | |
| Salesman | Q | 9 | 7 | 12 | 6 |
| R | 13 | 16 | 15 | 12 | |
| S | 14 | 10 | 12 | 11 | |
Advertisements
उत्तर
Here the number of rows and columns are equal.
∴ The given assignment problem is balanced.
Step 1: Select the smallest element in each row and subtract this from all the elements in its row.
| Area | |||||
| 1 | 2 | 3 | 4 | ||
| P | 3 | 9 | 0 | 8 | |
| Salesman | Q | 3 | 1 | 6 | 0 |
| R | 1 | 4 | 3 | 0 | |
| S | 4 | 0 | 2 | 1 | |
Step 2: Select the smallest element in each column and subtract this from all the elements in its column.
| Area | |||||
| 1 | 2 | 3 | 4 | ||
| P | 2 | 9 | 0 | 8 | |
| Salesman | Q | 2 | 1 | 6 | 0 |
| R | 0 | 4 | 3 | 0 | |
| S | 3 | 0 | 2 | 1 | |
Step 3: (Assignment)
Examine the rows with exactly one zero. Mark the zero by □ Mark other zeros in its column by X
| Area | |||||
| 1 | 2 | 3 | 4 | ||
| P | 2 | 9 | 0 | 8 | |
| Salesman | Q | 2 | 1 | 6 | 0 |
| R | 0 | 4 | 3 | 0 | |
| S | 3 | 0 | 2 | 1 | |
Thus all the four assignments have been made.
The optimal assignment schedule and total cost.
| Salesman | Area | Cost |
| P | 3 | 8 |
| Q | 4 | 6 |
| R | 1 | 13 |
| S | 2 | 10 |
| Total | 37 | |
The Optimum cost (minimum) = ₹ 37
APPEARS IN
संबंधित प्रश्न
A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:
| Jobs | Machines (Processing Cost in ₹) |
|||
| P | Q | R | S | |
| A | 31 | 25 | 33 | 29 |
| B | 25 | 24 | 23 | 21 |
| C | 19 | 21 | 23 | 24 |
| D | 38 | 36 | 34 | 40 |
Find the optimal assignment to minimize the total processing cost.
Five wagons are available at stations 1, 2, 3, 4, and 5. These are required at 5 stations I, II, III, IV, and V. The mileage between various stations are given in the table below. How should the wagons be transported so as to minimize the mileage covered?
| I | II | III | IV | V | |
| 1 | 10 | 5 | 9 | 18 | 11 |
| 2 | 13 | 9 | 6 | 12 | 14 |
| 3 | 3 | 2 | 4 | 4 | 5 |
| 4 | 18 | 9 | 12 | 17 | 15 |
| 5 | 11 | 6 | 14 | 19 | 10 |
The assignment problem is said to be balanced if ______.
State whether the following is True or False :
It is not necessary to express an assignment problem into n x n matrix.
Choose the correct alternative:
When an assignment problem has more than one solution, then it is ______
If the given matrix is ______ matrix, the assignment problem is called balanced problem
State whether the following statement is True or False:
The objective of an assignment problem is to assign number of jobs to equal number of persons at maximum cost
What is the Assignment problem?
Choose the correct alternative:
In an assignment problem involving four workers and three jobs, total number of assignments possible are
A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:
| To | |||||||
| 7 | 8 | 9 | 10 | 11 | 12 | ||
| From | 1 | 31 | 62 | 29 | 42 | 15 | 41 |
| 2 | 12 | 19 | 39 | 55 | 71 | 40 | |
| 3 | 17 | 29 | 50 | 41 | 22 | 22 | |
| 4 | 35 | 40 | 38 | 42 | 27 | 33 | |
| 5 | 19 | 30 | 29 | 16 | 20 | 33 | |
| 6 | 72 | 30 | 30 | 50 | 41 | 20 | |
How should the truck be dispersed so as to minimize the total distance travelled?
