Question
If 45 persons can complete a work in 20 days, then the time taken by 75 persons will be ______ hours.
Advertisements
Solution
If 45 persons can complete a work in 20 days, then the time taken by 75 persons will be 288 hours.
Explanation:
∵ 45 persons can complete a work in 20 days.
∴ 1 person can complete a work in 45 × 20 i.e. 900 days.
Similarly, 75 persons can complete the same work in `900/75` = 12 days
= 12 × 24 ...[∵ 1 day = 24 h]
= 288 h
APPEARS IN
RELATED QUESTIONS
68 boxes of a certain commodity require a shelf-length of 13.6 m. How many boxes of the same commodity would occupy a shelf length of 20.4 m?
11 men can dig \[6\frac{3}{4}\] metre long trench in one day. How many men should be employed for digging 27 metre long trench of the same type in one day?
In 15 days, the earth picks up 1.2 × 108 kg of dust from the atmosphere. In how many days it will pick up 4.8 × 108 kg of dust?
A postman can sort out 738 letters in 6 hours. How many letters can be sorted in 9 hours?
Two quantities are said to vary ______ with each other if they increase (decrease) together in such a manner that the ratio of their corresponding values remains constant.
When two quantities are related in such a manner that, if one increases, the other also increases, then they always vary directly.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Simple interest on a given sum and the rate of interest.
l varies directly as m and l is equal to 5, when `m = 2/3`. Find l when `m = 16/3`.
The mass of an aluminum rod varies directly with its length. If a 16 cm long rod has a mass of 192 g, find the length of the rod whose mass is 105 g.
Many schools have a recommended students-teacher ratio as 35:1. Next year, school expects an increase in enrolment by 280 students. How many new teachers will they have to appoint to maintain the students-teacher ratio?