Question
If 45 persons can complete a work in 20 days, then the time taken by 75 persons will be ______ hours.
Advertisements
Solution
If 45 persons can complete a work in 20 days, then the time taken by 75 persons will be 288 hours.
Explanation:
∵ 45 persons can complete a work in 20 days.
∴ 1 person can complete a work in 45 × 20 i.e. 900 days.
Similarly, 75 persons can complete the same work in `900/75` = 12 days
= 12 × 24 ...[∵ 1 day = 24 h]
= 288 h
APPEARS IN
RELATED QUESTIONS
Which of the following quantities vary directly with each other?
(i) Number of articles (x) and their price (y).
(ii) Weight of articles (x) and their cost (y).
(iii) Distance x and time y, speed remaining the same.
(iv) Wages (y) and number of hours (x) of work.
(v) Speed (x) and time (y) (distance covered remaining the same).
(vi) Area of a land (x) and its cost (y).
Mohan takes 9 hours to mow a large lawn. He and Sohan together can mow it in 4 hours. How long will Sohan take to mow the lawn if he works alone?
A pipe can fill a cistern in 10 hours. Due to a leak in the bottom it is filled in 12 hours. When the cistern is full, in how much time will it be emptied by the leak?
Every 3 months Tamilselvan deposits ₹ 5000 as savings in his bank account. In how many years he can save ₹ 1,50,000
A truck needs 54 litres of diesel for covering a distance of 297 km. The diesel required by the truck to cover a distance of 550 km is ______.
In which of the following case, do the quantities vary directly with each other?
Both x and y are in direct proportion, then `1/x` and `1/y` are ______.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Income tax and the income.
30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days?