प्रश्न
If 45 persons can complete a work in 20 days, then the time taken by 75 persons will be ______ hours.
Advertisements
उत्तर
If 45 persons can complete a work in 20 days, then the time taken by 75 persons will be 288 hours.
Explanation:
∵ 45 persons can complete a work in 20 days.
∴ 1 person can complete a work in 45 × 20 i.e. 900 days.
Similarly, 75 persons can complete the same work in `900/75` = 12 days
= 12 × 24 ...[∵ 1 day = 24 h]
= 288 h
APPEARS IN
संबंधित प्रश्न
Complite the following table given that x varies directly as y .
| x | 5 | ... | 10 | 35 | 25 | ... |
| y | 8 | 12 | ... | ... | ... | 32 |
The amount of extension in an elastic string varies directly as the weight hung on it. If a weight of 150 gm produces an extension of 2.9 cm, then what weight would produce an extension of 17.4 cm?
If 7 kg onions cost 140 rupees, how much must we pay for 12 kg onions?
If the cost of 3 books is ₹ 90, then find the cost of 12 books.
When the distance is kept fixed, speed and time vary directly with each other.
The area of cultivated land and the crop harvested is a case of direct proportion.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Distance travelled by an auto-rickshaw and time taken.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Sales Tax and the amount of the bill.
30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days?
A bowler throws a cricket ball at a speed of 120 km/h. How long does this ball take to travel a distance of 20 metres to reach the batsman?