English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 11

The critical path of the following network is - Business Mathematics and Statistics

Advertisements
Advertisements

Question

The critical path of the following network is

Options

  • 1 - 2 - 4 - 5

  • 1 - 3 - 5

  • 1 - 2 - 3 - 5

  • 1 - 2 - 3 - 4 - 5

MCQ
Advertisements

Solution

1 - 2 - 3 - 4 - 5

Explanation:

1 - 2 - 4 - 5 ⇒ EFT = 20 + 12 + 10 = 42

1 - 3 - 5 ⇒ EFT = 25 + 8 = 33

1 - 2 - 3 - 5 ⇒ EFT = 20 + 10 + 8 = 38

1 - 2 - 3 - 4 - 5 ⇒ EFT = 20 + 10 + 5 + 10 = 45

shaalaa.com
Network Analysis
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.3 [Page 250]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 11 TN Board
Chapter 10 Operations Research
Exercise 10.3 | Q 1 | Page 250

RELATED QUESTIONS

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.


One of the conditions for the activity (i, j) to lie on the critical path is


In a network while numbering the events which one of the following statements is false?


Which of the following is not correct?


In the context of network, which of the following is not correct


The objective of network analysis is to


The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×