English
Tamil Nadu Board of Secondary EducationHSC Commerce Class 11

The critical path of the following network is - Business Mathematics and Statistics

Advertisements
Advertisements

Question

The critical path of the following network is

Options

  • 1 - 2 - 4 - 5

  • 1 - 3 - 5

  • 1 - 2 - 3 - 5

  • 1 - 2 - 3 - 4 - 5

MCQ
Advertisements

Solution

1 - 2 - 3 - 4 - 5

Explanation:

1 - 2 - 4 - 5 ⇒ EFT = 20 + 12 + 10 = 42

1 - 3 - 5 ⇒ EFT = 25 + 8 = 33

1 - 2 - 3 - 5 ⇒ EFT = 20 + 10 + 8 = 38

1 - 2 - 3 - 4 - 5 ⇒ EFT = 20 + 10 + 5 + 10 = 45

shaalaa.com
Network Analysis
  Is there an error in this question or solution?
Chapter 10: Operations Research - Exercise 10.3 [Page 250]

APPEARS IN

Samacheer Kalvi Business Mathematics and Statistics [English] Class 11 TN Board
Chapter 10 Operations Research
Exercise 10.3 | Q 1 | Page 250

RELATED QUESTIONS

Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.


Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G


Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.


A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


In a network while numbering the events which one of the following statements is false?


Network problems have the advantage in terms of project


Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J

A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×