Question
Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?
Advertisements
Solution
| Number of men | No. of days | |
| Initially | 6 | 12 |
| 2 days later available work | 6 | 12 − 2 = 10 |
| Remaining work after 6 men joined | 6 + 6 = 12 | x |
As the number of men increases the number of days decreases.
∴ They are inversely proportional
x1y1 = x2y2
6 × 10 = 12 × x
x = `(6 xx 10)/12`
x = 5 days
∴ Remaining work will be complete in 5 days
APPEARS IN
RELATED QUESTIONS
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
If x and y vary inversely as other and x = 30, find y when constant of variation = 900.
Three persons can build a small house in 8 days. To build the same house in 6 days, how many persons are required?
16 taps can fill a petrol tank in 18 minutes. The time taken for 9 taps to fill the same tank will be _________ minutes
Forty students stay in a hostel. They had food stock for 30 days. If the students are doubled then for how many days the stock will last?
If one angle of a triangle is kept fixed then the measure of the remaining two angles vary inversely with each other.
If x varies inversely as y and when x = 6, y = 8, then for x = 8 the value of y is 10.
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
If a and b vary inversely to other, then find the values of p, q, r ; x, y, z and l, m, n.
| a | 2 | y | 6 | 10 |
| b | x | 12.5 | 15 | z |