Question
Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?
Advertisements
Solution
| Number of men | No. of days | |
| Initially | 6 | 12 |
| 2 days later available work | 6 | 12 − 2 = 10 |
| Remaining work after 6 men joined | 6 + 6 = 12 | x |
As the number of men increases the number of days decreases.
∴ They are inversely proportional
x1y1 = x2y2
6 × 10 = 12 × x
x = `(6 xx 10)/12`
x = 5 days
∴ Remaining work will be complete in 5 days
APPEARS IN
RELATED QUESTIONS
In a hostel of 50 girls, there are food provisions for 40 days. If 30 more girls join the hostel, how long will these provisions last?
A group of 3 friends staying together, consume 54 kg of wheat every month. Some more friends join this group and they find that the same amount of wheat lasts for 18 days. How many new members are there in this group now?
A person has money to buy 25 cycles worth Rs 500 each. How many cycles he will be able to buy if each cycle is costing Rs 125 more?
Mary cycles at 6 km per hour. How long will she take to reach her Aunt’s house which is 12 km away? If she cycles at a speed of 4 km/hr, how long would she take?
If two quantities p and q vary inversely with each other then ______ of their corresponding values remains constant.
If x varies inversely as y and x = 4 when y = 6, then when x = 3 the value of y is ______.
If d varies directly as t2, then we can write dt2 = k, where k is some constant.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Compound interest on a given sum and the sum invested.
If x varies inversely as y and y = 60 when x = 1.5. Find x. when y = 4.5.
At a particular time, the length of the shadow of Qutub Minar whose height is 72 m is 80 m. What will be the height of an electric pole, the length of whose shadow at the same time is 1000 cm?