Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?
Advertisements
उत्तर
| Number of men | No. of days | |
| Initially | 6 | 12 |
| 2 days later available work | 6 | 12 − 2 = 10 |
| Remaining work after 6 men joined | 6 + 6 = 12 | x |
As the number of men increases the number of days decreases.
∴ They are inversely proportional
x1y1 = x2y2
6 × 10 = 12 × x
x = `(6 xx 10)/12`
x = 5 days
∴ Remaining work will be complete in 5 days
APPEARS IN
संबंधित प्रश्न
It x and y vary inversely, fill in the following blank:
| x | 16 | 32 | 8 | 128 |
| y | 4 | ... | ... | 0.25 |
16 taps can fill a petrol tank in 18 minutes. The time taken for 9 taps to fill the same tank will be _________ minutes
A farmer has enough food for 144 ducks for 28 days. If he sells 32 ducks how long will the food last?
12 cows can graze a field for 10 days. 20 cows can graze the same field for _______ days
4 typists are employed to complete a work in 12 days. If two more typists are added, they will finish the same work in _________ days
If a tree 24 m high casts a shadow of 15 m, then the height of a pole that casts a shadow of 6 m under similar conditions is 9.6 m.
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
Sobi types 108 words in 6 minutes. How many words would she type in half an hour?
If a deposit of Rs 2,000 earns an interest of Rs 500 in 3 years, how much interest would a deposit of Rs 36,000 earn in 3 years with the same rate of simple interest?
The variable x is inversely proportional to y. If x increases by p%, then by what per cent will y decrease?