Advertisements
Advertisements
प्रश्न
Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?
Advertisements
उत्तर
| Number of men | No. of days | |
| Initially | 6 | 12 |
| 2 days later available work | 6 | 12 − 2 = 10 |
| Remaining work after 6 men joined | 6 + 6 = 12 | x |
As the number of men increases the number of days decreases.
∴ They are inversely proportional
x1y1 = x2y2
6 × 10 = 12 × x
x = `(6 xx 10)/12`
x = 5 days
∴ Remaining work will be complete in 5 days
APPEARS IN
संबंधित प्रश्न
Which of the following are in inverse proportion?
The time taken for a journey and the distance travelled in a uniform speed.
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
Three spraying machines working together can finish painting a house in 60 minutes. How long will it take for 5 machines of the same capacity to do the same job?
If x and y vary inversely as other and x = 3 when y = 8, find y when x = 4 .
16 taps can fill a petrol tank in 18 minutes. The time taken for 9 taps to fill the same tank will be _________ minutes
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Neelaveni goes by bicycle to her school every day. Her average speed is 12 km/hr and she reaches school in 20 minutes. What is the increase in speed, If she reaches the school in 15 minutes?
Which quantities in the previous question vary inversely with each other?
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?