प्रश्न
Two persons could fit new windows in house in 3 days.
How many persons would be needed to fit the windows in one day?
Advertisements
उत्तर
Let the number of persons required to fit all the windows in one day be y. The following table is formed.
| Number of persons | 2 | y |
| Number of days | 3 | 1 |
The lesser the number of days, the more will be the number of persons required to fit all the windows. Hence, this is a case of inverse proportion. Therefore,
2 × 3 = y × 1
y = 6
Hence, 6 persons are required to fit all the windows in one day.
APPEARS IN
संबंधित प्रश्न
If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
55 cows can graze a field in 16 days. How many cows will graze the same field in 10 days?
A person has money to buy 25 cycles worth Rs 500 each. How many cycles he will be able to buy if each cycle is costing Rs 125 more?
Mary cycles at 6 km per hour. How long will she take to reach her Aunt’s house which is 12 km away? If she cycles at a speed of 4 km/hr, how long would she take?
If 40 workers can do a project work in 8 days, then _________ workers can do it in 4 days
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
A toy company requires 36 machines to produce car toys in 54 days. How many machines would be required to produce the same number of car toys in 81 days?
A printer, prints a book of 300 pages at the rate of 30 pages per minute. Then, how long will it take to print the same book if the speed of the printer is 25 pages per minute?
Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?
Two quantities are said to vary ______ with each other if an increase in one causes a decrease in the other in such a manner that the product of their corresponding values remains constant.