प्रश्न
A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
Advertisements
उत्तर
Let x be the extra number of men employed to complete the job in 7 months.
| Number of men | 420 | x |
| Months | 9 | 7 |
\[\text{ Since the number of men hired and the time required to finish the piece of work are in inverse variation, we have } : \]
\[420 \times 9 = 7x\]
\[ \Rightarrow x = \frac{420 \times 9}{7}\]
\[ = 540\]
\[\text{ Thus, the number of extra men required to complete the job in 7 months } = 540 - 420 = 120\]
APPEARS IN
संबंधित प्रश्न
Which of the following are in inverse proportion?
Area of cultivated land and the crop harvested
In which of the following table x and y vary inversely:
| x | 5 | 20 | 10 | 4 |
| y | 20 | 5 | 10 | 25 |
Which of the following quantities vary inversely as other?
The number of x men hired to construct a wall and the time y taken to finish the job.
It is known that for a given mass of gas, the volume v varies inversely as the pressure p. Fill in the missing entries in the following table:
| v (in cm3) | ... | 48 | 60 | ... | 100 | ... | 200 |
| p (in atmospheres) | 2 | ... | 3/2 | 1 | ... | 1/2 | ... |
If x and y vary inversely as other and x = 3 when y = 8, find y when x = 4 .
A farmer has enough food for 144 ducks for 28 days. If he sells 32 ducks how long will the food last?
It takes 120 minutes to weed a garden with 6 gardeners. If the same work is to be done in 30 minutes, how many more gardeners are needed?
4 typists are employed to complete a work in 12 days. If two more typists are added, they will finish the same work in _________ days
If 12 pumps can empty a reservoir in 20 hours, then time required by 45 such pumps to empty the same reservoir is ______ hours.
In case of inverse proportion, `a_2/- = b_2/-`