Question
A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
Advertisements
Solution
Let x be the extra number of men employed to complete the job in 7 months.
| Number of men | 420 | x |
| Months | 9 | 7 |
\[\text{ Since the number of men hired and the time required to finish the piece of work are in inverse variation, we have } : \]
\[420 \times 9 = 7x\]
\[ \Rightarrow x = \frac{420 \times 9}{7}\]
\[ = 540\]
\[\text{ Thus, the number of extra men required to complete the job in 7 months } = 540 - 420 = 120\]
APPEARS IN
RELATED QUESTIONS
If a box of sweets is divided among 24 children, they will get 5 sweets each. How many would each get, if the number of the children is reduced by 4?
A school has 8 periods a day each of 45 minutes duration. How long would each period be, if the school has 9 periods a day, assuming the number of school hours to be the same?
It x and y vary inversely, fill in the following blank:
| x | 16 | 32 | 8 | 128 |
| y | 4 | ... | ... | 0.25 |
16 taps can fill a petrol tank in 18 minutes. The time taken for 9 taps to fill the same tank will be _________ minutes
A farmer has enough food for 144 ducks for 28 days. If he sells 32 ducks how long will the food last?
12 cows can graze a field for 10 days. 20 cows can graze the same field for _______ days
10 farmers can plough a field in 21 days. Find the number of days reduced if 14 farmers ploughed the same field?
Which of the following vary inversely with each other?
In case of inverse proportion, `a_2/- = b_2/-`
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
The time taken by a train to cover a fixed distance and the speed of the train.