Question
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
Advertisements
Solution
Let x be the number days required to complete a piece of work by 125 men.
| Number of men | 50 | 125 |
| Months | 5 | x |
\[\text{ Since the number of men engaged and the number of days taken to do a piece of work are in inverse variation, we have: } \]
\[ 50 \times 5 = 125x\]
\[ \Rightarrow x = \frac{50 \times 5}{125}\]
\[ = 2\]
\[\text{ Thus, the required number of months is 2 } .\]
RELATED QUESTIONS
Two persons could fit new windows in house in 3 days.
One of the persons fell ill before the work started. How long would the job take now?
A school has 8 periods a day each of 45 minutes duration. How long would each period be, if the school has 9 periods a day, assuming the number of school hours to be the same?
It x and y vary inversely, fill in the following blank:
| x | 9 | ... | 81 | 243 |
| y | 27 | 9 | ... | 1 |
In a hostel of 50 girls, there are food provisions for 40 days. If 30 more girls join the hostel, how long will these provisions last?
16 taps can fill a petrol tank in 18 minutes. The time taken for 9 taps to fill the same tank will be _________ minutes
6 pumps are required to fill a water sump in 1 hr 30 minutes. What will be the time taken to fill the sump if one pump is switched off?
Forty students stay in a hostel. They had food stock for 30 days. If the students are doubled then for how many days the stock will last?
If x and y are in inverse proportion, then (x + 1) and (y + 1) are also in inverse proportion.
If x varies inversely as y and x = 20 when y = 600, find y when x = 400.
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?