Question
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
Advertisements
Solution
Let x be the number days required to complete a piece of work by 125 men.
| Number of men | 50 | 125 |
| Months | 5 | x |
\[\text{ Since the number of men engaged and the number of days taken to do a piece of work are in inverse variation, we have: } \]
\[ 50 \times 5 = 125x\]
\[ \Rightarrow x = \frac{50 \times 5}{125}\]
\[ = 2\]
\[\text{ Thus, the required number of months is 2 } .\]
RELATED QUESTIONS
Which of the following are in inverse proportion?
The number of workers on a job and the time to complete the job.
A factory required 42 machines to produce a given number of articles in 63 days. How many machines would be required to produce the same number of articles in 54 days?
In which of the following table x and y vary inversely:
| x | 4 | 3 | 6 | 1 |
| y | 9 | 12 | 8 | 36 |
It x and y vary inversely, fill in the following blank:
| x | 16 | 32 | 8 | 128 |
| y | 4 | ... | ... | 0.25 |
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
In case of inverse proportion, `a_2/- = b_2/-`
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
The time taken by a train to cover a fixed distance and the speed of the train.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Increase in cost and number of shirts that can be purchased if the budget remains the same.
At a particular time, the length of the shadow of Qutub Minar whose height is 72 m is 80 m. What will be the height of an electric pole, the length of whose shadow at the same time is 1000 cm?
The variable x is inversely proportional to y. If x increases by p%, then by what per cent will y decrease?