प्रश्न
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
Advertisements
उत्तर
Let x be the number days required to complete a piece of work by 125 men.
| Number of men | 50 | 125 |
| Months | 5 | x |
\[\text{ Since the number of men engaged and the number of days taken to do a piece of work are in inverse variation, we have: } \]
\[ 50 \times 5 = 125x\]
\[ \Rightarrow x = \frac{50 \times 5}{125}\]
\[ = 2\]
\[\text{ Thus, the required number of months is 2 } .\]
APPEARS IN
संबंधित प्रश्न
Which of the following are in inverse proportion?
The time taken for a fixed journey and the speed of the vehicle.
If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
A car can finish a certain journey in 10 hours at the speed of 48 km/hr. By how much should its speed be increased so that it may take only 8 hours to cover the same distance?
Mary cycles at 6 km per hour. How long will she take to reach her Aunt’s house which is 12 km away? If she cycles at a speed of 4 km/hr, how long would she take?
It takes 120 minutes to weed a garden with 6 gardeners. If the same work is to be done in 30 minutes, how many more gardeners are needed?
x varies inversely as twice of y. Given that when y = 6, the value of x is 4. Find the value of x when y = 8
When two quantities x and y are in ______ proportion or vary ______ they are written as `x oo 1/y`.
If x varies inversely as y, then
| x | – | 60 |
| y | 2 | 10 |
If p and q are in inverse variation then (p + 2) and (q – 2) are also in inverse proportion.
Sobi types 108 words in 6 minutes. How many words would she type in half an hour?