A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
Advertisements
उत्तर
Let x be the number days required to complete a piece of work by 125 men.
| Number of men | 50 | 125 |
| Months | 5 | x |
\[\text{ Since the number of men engaged and the number of days taken to do a piece of work are in inverse variation, we have: } \]
\[ 50 \times 5 = 125x\]
\[ \Rightarrow x = \frac{50 \times 5}{125}\]
\[ = 2\]
\[\text{ Thus, the required number of months is 2 } .\]
संबंधित प्रश्न
If a box of sweets is divided among 24 children, they will get 5 sweets each. How many would each get, if the number of the children is reduced by 4?
A farmer has enough food to feed 20 animals in his cattle for 6 days. How long would the food last if there were 10 more animals in his cattle?
A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
55 cows can graze a field in 16 days. How many cows will graze the same field in 10 days?
Mohanrao took 10 days to finish a book, reading 40 pages every day. How many pages must be read in a day to finish it in 8 days?
Forty students stay in a hostel. They had food stock for 30 days. If the students are doubled then for how many days the stock will last?
Meena had enough money to send 8 parcels each weighing 500 grams through a courier service. What would be the weight of each parcel, if she has to send 40 parcels for the same money?
If x and y are in inverse proportion, then (x + 1) and (y + 1) are also in inverse proportion.
If x varies inversely as y and y = 60 when x = 1.5. Find x. when y = 4.5.
Two persons could fit new windows in house in 3 days.
How many persons would be needed to fit the windows in one day?