प्रश्न
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Advertisements
उत्तर
Let the number of days required be x.
| Number of machines | 10 | 30 |
| Number of days | 60 | x |
As the number of machines increases it takes less days to complete the work
∴ They are in inverse proportion, x1y1 = x2y2
10 × 60 = 30 × x
x = `(10 xx 60)/30`, x = 20
It takes 20 days to dig the hole
APPEARS IN
संबंधित प्रश्न
Which of the following are in inverse proportion?
The population of a country and the area of land per person.
A factory required 42 machines to produce a given number of articles in 63 days. How many machines would be required to produce the same number of articles in 54 days?
Which of the following quantities vary inversely as other?
The length x of a journey by bus and price y of the ticket.
1200 soldiers in a fort had enough food for 28 days. After 4 days, some soldiers were transferred to another fort and thus the food lasted now for 32 more days. How many soldiers left the fort?
12 cows can graze a field for 10 days. 20 cows can graze the same field for _______ days
x varies inversely as twice of y. Given that when y = 6, the value of x is 4. Find the value of x when y = 8
Which of the following vary inversely with each other?
If two quantities p and q vary inversely with each other, then ______
If x varies inversely as y, then
| x | – | 60 |
| y | 2 | 10 |
In a hostel of 50 girls, there are food provisions for 40 days. If 30 more girls join the hostel, how long will these provisions last?