प्रश्न
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Advertisements
उत्तर
Let the number of days required be x.
| Number of machines | 10 | 30 |
| Number of days | 60 | x |
As the number of machines increases it takes less days to complete the work
∴ They are in inverse proportion, x1y1 = x2y2
10 × 60 = 30 × x
x = `(10 xx 60)/30`, x = 20
It takes 20 days to dig the hole
APPEARS IN
संबंधित प्रश्न
If a box of sweets is divided among 24 children, they will get 5 sweets each. How many would each get, if the number of the children is reduced by 4?
A batch of bottles was packed in 25 boxes with 12 bottles in each box. If the same batch is packed using 20 bottles in each box, how many boxes would be filled?

It is known that for a given mass of gas, the volume v varies inversely as the pressure p. Fill in the missing entries in the following table:
| v (in cm3) | ... | 48 | 60 | ... | 100 | ... | 200 |
| p (in atmospheres) | 2 | ... | 3/2 | 1 | ... | 1/2 | ... |
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
If x and y vary inversely as other and x = 3 when y = 8, find y when x = 4 .
Five workers take 12 days to weed a field. How many days would 6 workers take? How many would 15 take?
Neelaveni goes by bicycle to her school every day. Her average speed is 12 km/hr and she reaches school in 20 minutes. What is the increase in speed, If she reaches the school in 15 minutes?
Both x and y are said to vary ______ with each other if for some positive number k, xy = k.
If p and q are in inverse variation then (p + 2) and (q – 2) are also in inverse proportion.
If x varies inversely as y and y = 60 when x = 1.5. Find x. when y = 4.5.