Question
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Advertisements
Solution
Let the number of days required be x.
| Number of machines | 10 | 30 |
| Number of days | 60 | x |
As the number of machines increases it takes less days to complete the work
∴ They are in inverse proportion, x1y1 = x2y2
10 × 60 = 30 × x
x = `(10 xx 60)/30`, x = 20
It takes 20 days to dig the hole
APPEARS IN
RELATED QUESTIONS
A car takes 2 hours to reach a destination by travelling at the speed of 60 km/h. How long will it take when the car travels at the speed of 80 km/h?
Two persons could fit new windows in house in 3 days.
One of the persons fell ill before the work started. How long would the job take now?
In which of the following table x and y vary inversely:
| x | 5 | 20 | 10 | 4 |
| y | 20 | 5 | 10 | 25 |
It x and y vary inversely, fill in the following blank:
| x | 9 | ... | 81 | 243 |
| y | 27 | 9 | ... | 1 |
If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
Mohanrao took 10 days to finish a book, reading 40 pages every day. How many pages must be read in a day to finish it in 8 days?
Which quantities in the previous question vary inversely with each other?
If x varies inversely as y and when x = 6, y = 8, then for x = 8 the value of y is 10.
If x varies inversely as y and x = 20 when y = 600, find y when x = 400.
In a hostel of 50 girls, there are food provisions for 40 days. If 30 more girls join the hostel, how long will these provisions last?