Question
It takes 120 minutes to weed a garden with 6 gardeners. If the same work is to be done in 30 minutes, how many more gardeners are needed?
Advertisements
Solution
Let the, number of gardeners needed be x.
| Number of gardeners | 6 | x |
| Time in minutes | 120 | 30 |
As the number of gardeners increases the time decreases.
They are in inverse proportion,
x1y1 = x2y2
6 × 120 = x × 30
x = `(6 xx 120)/30`
x = 24
∴ To complete the work in 30 min gardeners needed = 24
Already existing gardeners = 6
∴ More gardeners needed = 24 – 6 = 18
18 more gardeners are needed
APPEARS IN
RELATED QUESTIONS
If a box of sweets is divided among 24 children, they will get 5 sweets each. How many would each get, if the number of the children is reduced by 4?
A contractor estimates that 3 persons could rewire Jasminder’s house in 4 days. If, he uses 4 persons instead of three, how long should they take to complete the job?
A factory required 42 machines to produce a given number of articles in 63 days. How many machines would be required to produce the same number of articles in 54 days?
55 cows can graze a field in 16 days. How many cows will graze the same field in 10 days?
If 40 workers can do a project work in 8 days, then _________ workers can do it in 4 days
12 cows can graze a field for 10 days. 20 cows can graze the same field for _______ days
In a school there is 7 periods a day each of 45 minutes duration. How long each period is if the school has 9 periods a day assuming the number of hours to be the same?
If xy = 10, then x and y vary ______ with each other.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
Compound interest on a given sum and the sum invested.
Two persons could fit new windows in house in 3 days.
How many persons would be needed to fit the windows in one day?