प्रश्न
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Advertisements
उत्तर
Let the number of days required be x.
| Number of machines | 10 | 30 |
| Number of days | 60 | x |
As the number of machines increases it takes less days to complete the work
∴ They are in inverse proportion, x1y1 = x2y2
10 × 60 = 30 × x
x = `(10 xx 60)/30`, x = 20
It takes 20 days to dig the hole
APPEARS IN
संबंधित प्रश्न
Which of the following are in inverse proportion?
The number of workers on a job and the time to complete the job.
It x and y vary inversely, fill in the following blank:
| x | 12 | 16 | ... | 8 | ... |
| y | ... | 6 | 4 | ... | 0.25 |
It is known that for a given mass of gas, the volume v varies inversely as the pressure p. Fill in the missing entries in the following table:
| v (in cm3) | ... | 48 | 60 | ... | 100 | ... | 200 |
| p (in atmospheres) | 2 | ... | 3/2 | 1 | ... | 1/2 | ... |
55 cows can graze a field in 16 days. How many cows will graze the same field in 10 days?
Five workers take 12 days to weed a field. How many days would 6 workers take? How many would 15 take?
6 pipes are required to fill a tank in 1 hour 20 minutes. How long will it take if only 5 pipes of the same type are used?
A flood relief camp has food stock by which 80 people can be benefited for 60 days. After 10 days 20 more people have joined the camp. Calculate the number of days of food shortage due to the addition of 20 more people?
If x varies inversely as y, then
| x | – | 60 |
| y | 2 | 10 |
If x varies inversely as y and y = 60 when x = 1.5. Find x. when y = 4.5.
Find the values of x and y if a and b are in inverse proportion:
- 12 x 8
- 30 5 y