प्रश्न
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Advertisements
उत्तर
Let the number of days required be x.
| Number of machines | 10 | 30 |
| Number of days | 60 | x |
As the number of machines increases it takes less days to complete the work
∴ They are in inverse proportion, x1y1 = x2y2
10 × 60 = 30 × x
x = `(10 xx 60)/30`, x = 20
It takes 20 days to dig the hole
APPEARS IN
संबंधित प्रश्न
Find the constant of variation from the table given below:
| x | 3 | 5 | 7 | 9 |
| y | 12 | 20 | 28 | 36 |
Set up a table and solve the following problems. Use unitary method to verify the answer.
In which of the following table x and y vary inversely:
| x | 5 | 20 | 10 | 4 |
| y | 20 | 5 | 10 | 25 |
Which of the following quantities vary inversely as other?
Journey (x km) undertaken by a car and the petrol (y litres) consumed by it.
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
A car can finish a certain journey in 10 hours at the speed of 48 km/hr. By how much should its speed be increased so that it may take only 8 hours to cover the same distance?
6 pumps are required to fill a water sump in 1 hr 30 minutes. What will be the time taken to fill the sump if one pump is switched off?
If xy = 10, then x and y vary ______ with each other.
When two quantities x and y are in ______ proportion or vary ______ they are written as `x oo 1/y`.
When the speed is kept fixed, time and distance vary inversely with each other.
If x varies inversely as y and y = 60 when x = 1.5. Find x. when y = 4.5.