प्रश्न

A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?

थोडक्यात उत्तर
Advertisements

उत्तर

Let x be the extra number of men employed to complete the job in 7 months.
 

Number of men 420 x
Months 9 7

\[\text{ Since the number of men hired and the time required to finish the piece of work are in inverse variation, we have } : \]
\[420 \times 9 = 7x\]
\[ \Rightarrow x = \frac{420 \times 9}{7}\]
\[ = 540\]
\[\text{ Thus, the number of extra men required to complete the job in 7 months }  = 540 - 420 = 120\]

shaalaa.com
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?

व्हिडिओ ट्यूटोरियलVIEW ALL [1]

संबंधित प्रश्‍न

A school has 8 periods a day each of 45 minutes duration. How long would each period be, if the school has 9 periods a day, assuming the number of school hours to be the same?


Find the constant of variation from the table given below:

x 3 5 7 9
y 12 20 28 36

Set up a table and solve the following problems. Use unitary method to verify the answer.


In which of the following table x and y vary inversely: 

x 4 3 12 1
y 6 8 2 24

Which of the following quantities vary inversely as other?

The number of x men hired to construct a wall and the time y taken to finish the job.


Raghu has enough money to buy 75 machines worth Rs 200 each. How many machines can he buy if he gets a discount of Rs 50 on each machine?


6 pumps are required to fill a water sump in 1 hr 30 minutes. What will be the time taken to fill the sump if one pump is switched off?


If two quantities p and q vary inversely with each other, then ______


Write whether the following statement vary directly, vary inversely with each other, or neither of the two.

The height of a tree and the number of years.


A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?