Question

A tank is connected to three pipes – Pipe A, B, and C. Pipe A can fill the tank in 6 hours,  B can fill the tank in 8 hours and Pipe C can empty the full tank in 12 hours. How much time will it take to fill the tank completely if all three pipes are working together? 

Options

  • 4 hours 

  • 4 hours 48 minutes

  • 5 hours

  • 5 hours 20 minutes

MCQ
Advertisements

Solution

4 hours 48 minutes

Explanation:

A portion of a tank filled in 1 hour, when pipe A, B, and C are working together

`=1/6+1/8-1/12`

`=(4+3-2)/24=5/24` tank

Hence, the time required to fill the tank`=24/5` hours

= 4.8 hours

= 4 hours 48 minutes.

shaalaa.com
Time and Work (Entrance Exam)
  Is there an error in this question or solution?
2018-2019 (May) Set 1

RELATED QUESTIONS

Choose the most appropriate option.

Two men and seven boys can do work in 14 days. Three men and eight boys can do the same work in 11 days. Further, eight men and six boys can do three times the amount of this work in:


16 men can do a piece of work in 16 days. 4 days after they started the work 8 more men joined them. How many days will they now take to complete the remaining work?


A can do a piece of work in 20 days and B can do the same work in 15 days. How long will they take to finish the work, if both work together?


A water tank has eight pipes fitted into it. Pipes are of two types: Green Pipe and Red Pipe. Green pipes are used to fill the tank and the Red pipes are used to empty the tank. Every Green pipe can fill the tank in 12 hours and every Red pipe can empty it in 36 hours. On opening all the pipes an empty tank is filled in 3 hours. The number of Red pipe is


A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in


Twenty women can do a piece of work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?


A, B and C can do a piece of work in 20, 30 and 60 days, respectively. In how many days can A do the work, if he is assisted by B and C on every third day?


A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for ₹ 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?


Five men can complete a piece of work in 24 days. In how many days will 12 men complete the same piece of work?


A project manager hired 16 men to complete a project in 38 days. However, after 30 days, he realized that only `5/9`th of the work is complete. How many more men does he need to hire to complete the project on time?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×