A tank is connected to three pipes – Pipe A, B, and C. Pipe A can fill the tank in 6 hours, B can fill the tank in 8 hours and Pipe C can empty the full tank in 12 hours. How much time will it take to fill the tank completely if all three pipes are working together?
विकल्प
4 hours
4 hours 48 minutes
5 hours
5 hours 20 minutes
Advertisements
उत्तर
4 hours 48 minutes
Explanation:
A portion of a tank filled in 1 hour, when pipe A, B, and C are working together
`=1/6+1/8-1/12`
`=(4+3-2)/24=5/24` tank
Hence, the time required to fill the tank`=24/5` hours
= 4.8 hours
= 4 hours 48 minutes.
APPEARS IN
संबंधित प्रश्न
Choose the most appropriate option
‘A’ and ‘B’ complete a work in 12 days, ‘B’ and ‘C’ in 8 days and ‘C’ and ‘A’ in 16 days. ‘A’ left after working for 3 days. In how many days more will ‘B’ and ‘C’ finish the remaining work?
Solve the following question and mark the best possible option.
It takes 8 people working at equal rates to finish work in 96 days. How long will 6 workers take to finish the same work?
16 men can do a piece of work in 16 days. 4 days after they started the work 8 more men joined them. How many days will they now take to complete the remaining work?
Aarti can do a piece of work in 6 days. In how many days will she complete three times of work of the same type?
A and B can together finish work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days, A alone can finish the work?
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a computer, while Kumar takes 5 hours to type 40 pages. How much time will they take, working together on two different computers to type an assignment of 110 pages?
Two men A and B, each working alone by working 12 hours per day, can complete a work in 20 days. For execution of the work, it was decided that A and B would be working for 8 and 6 hours per day, respectively, on alternate days starting with A. If it takes x days and y hours to complete the work then (x, y) is:
Working 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days?
A project manager hired 16 men to complete a project in 38 days. However, after 30 days, he realized that only `5/9`th of the work is complete. How many more men does he need to hire to complete the project on time?