A Tank is Connected to Three Pipes – Pipe A, B, and C. Pipe a Can Fill the Tank in 6 Hours, B Can Fill the Tank in 8 Hours and Pipe C Can Empty the Full Tank in 12 Hours. How Much Time - Mathematics

Advertisements
Advertisements

प्रश्न

A tank is connected to three pipes – Pipe A, B, and C. Pipe A can fill the tank in 6 hours,  B can fill the tank in 8 hours and Pipe C can empty the full tank in 12 hours. How much time will it take to fill the tank completely if all three pipes are working together? 

विकल्प

  • 4 hours 

  • 4 hours 48 minutes

  • 5 hours

  • 5 hours 20 minutes

MCQ
Advertisements

उत्तर

4 hours 48 minutes

Explanation:

A portion of a tank filled in 1 hour, when pipe A, B, and C are working together

`=1/6+1/8-1/12`

`=(4+3-2)/24=5/24` tank

Hence, the time required to fill the tank`=24/5` hours

= 4.8 hours

= 4 hours 48 minutes.

shaalaa.com
Time and Work (Entrance Exam)
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
2018-2019 (May) Set 1

संबंधित प्रश्न

Choose the most appropriate option

‘A’ and ‘B’ complete a work in 12 days, ‘B’ and ‘C’ in 8 days and ‘C’ and ‘A’ in 16 days. ‘A’ left after working for 3 days. In how many days more will ‘B’ and ‘C’ finish the remaining work?


Choose the most appropriate option.

Two men and seven boys can do work in 14 days. Three men and eight boys can do the same work in 11 days. Further, eight men and six boys can do three times the amount of this work in:


A can do a piece of work in 20 days and B can do the same work in 15 days. How long will they take to finish the work, if both work together?


A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?


A, B and C can do a piece of work in 20, 30 and 60 days, respectively. In how many days can A do the work, if he is assisted by B and C on every third day?


A, B, and C get  ₹5400 for doing work in 36 days. A and C get ₹1880 for doing the same work in 20 days, which B and C get ₹3040 for doing the same work in 40 days. Find the amount received by C per day.


Two pipes P and Q can fill a tank in 15 min and 20 min, respectively. Both the pipes are opened together but after 4 min, pipe P is turned off. What is the total time required to fill the tank?


Vikas can complete a job in 15 days. Babin can do the same job in 10 days. In how many days can they complete the job if they work together?


26 men can complete a piece of work in 17 days. How many more men must be hired to complete the work in 13 days?


B is `4/3` times as efficient as A. If A can complete `5/8`th of a given task in 15 days, what fraction of the same task would remain incomplete if B works on it independently for 10 days only?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×