प्रश्न

A tank is connected to three pipes – Pipe A, B, and C. Pipe A can fill the tank in 6 hours,  B can fill the tank in 8 hours and Pipe C can empty the full tank in 12 hours. How much time will it take to fill the tank completely if all three pipes are working together? 

विकल्प

  • 4 hours 

  • 4 hours 48 minutes

  • 5 hours

  • 5 hours 20 minutes

MCQ
Advertisements

उत्तर

4 hours 48 minutes

Explanation:

A portion of a tank filled in 1 hour, when pipe A, B, and C are working together

`=1/6+1/8-1/12`

`=(4+3-2)/24=5/24` tank

Hence, the time required to fill the tank`=24/5` hours

= 4.8 hours

= 4 hours 48 minutes.

shaalaa.com
Time and Work (Entrance Exam)
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
2018-2019 (May) Set 1

संबंधित प्रश्न

Choose the most appropriate option

‘A’ and ‘B’ complete a work in 12 days, ‘B’ and ‘C’ in 8 days and ‘C’ and ‘A’ in 16 days. ‘A’ left after working for 3 days. In how many days more will ‘B’ and ‘C’ finish the remaining work?


Solve the following question and mark the best possible option.
It takes 8 people working at equal rates to finish work in 96 days. How long will 6 workers take to finish the same work?


16 men can do a piece of work in 16 days. 4 days after they started the work 8 more men joined them. How many days will they now take to complete the remaining work?


Aarti can do a piece of work in 6 days. In how many days will she complete three times of work of the same type?


A and B can together finish work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days, A alone can finish the work?


X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?


Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a computer, while Kumar takes 5 hours to type 40 pages. How much time will they take, working together on two different computers to type an assignment of 110 pages?


Two men A and B, each working alone by working 12 hours per day, can complete a work in 20 days. For execution of the work, it was decided that A and B would be working for 8 and 6 hours per day, respectively, on alternate days starting with A. If it takes x days and y hours to complete the work then (x, y) is:


Working 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days?


A project manager hired 16 men to complete a project in 38 days. However, after 30 days, he realized that only `5/9`th of the work is complete. How many more men does he need to hire to complete the project on time?