Two Men and Seven Boys Can Do a Work in 14 Days. Three Men and Eight Boys Can Do the Same Work in 11 Days. Further Eight Men and Six Boys Can Do Three Times the Amount of this Work In:

Advertisements
Advertisements

Question

Choose the most appropriate option.

Two men and seven boys can do work in 14 days. Three men and eight boys can do the same work in 11 days. Further, eight men and six boys can do three times the amount of this work in:

Options

  • 18 days

  • 21 days

  • 30 days

  • 24 days

MCQ
Advertisements

Solution

21 days

Explanation:

According to question

(2 × 14) men + (7 × 14) boys = (3 × 11) men + (8 × 11) boys

⇒ 5 men = 10 boys or 1 man = 2 boys

∴ (2 men + 7 boys) = (2 × 2 + 7) boys = 11 boys

(8 men + 6 boys) = (8 × 2 + 6) boys = 22 boys

Let the required number of days be x

According to the ratio proportion,

Boys 22: 11 Work 1: 3] :: 14 : x

∴ (22 × 1 × x) = (11 × 3 × 14)

`∴"x"=462/22=21`

Hence, the required number of days = 21.

shaalaa.com
Time and Work (Entrance Exam)
  Is there an error in this question or solution?
2016-2017 (May) Set 1

RELATED QUESTIONS

Twenty-five workers were employed to complete a compound wall in 12 days. Five workers left after working for 4 days. The remaining 20 workers completed the work. In how many days the total job was completed?


A contractor Abhay Singh employed some men to do a piece of work which can be done by 16 men in 14 days. At the end of 5 days, 7 of the men stopped working and 3 days later half of the remainder stopped working; the rest finished the work in 5 days. What is the number of men originally employed?


In a call center, 6 employees working for 10 hours complete a certain task. They started working at 11:00 a.m. This continued till 5.00 pm and after that, for each hour one more employee is added till the work gets completed. At what time will they complete the work?


Pipes P and Q can fill a tank in 5 and 6 h respectively. Pipe R can empty it in 12 h. If all the three pipes are opened together, then the tank will be filled in :


A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished?


A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:


8 boys and 12 girls together can finish a project work in 5 days. If it takes 50 days for one boy alone to finish the same project, how many days are required for one girl alone to complete the same project work?


Two men A and B, each working alone by working 12 hours per day, can complete a work in 20 days. For execution of the work, it was decided that A and B would be working for 8 and 6 hours per day, respectively, on alternate days starting with A. If it takes x days and y hours to complete the work then (x, y) is:


Puja is 30% less efficient than Poonam. If Poonam takes 20 days to do a job, how many days would Puja take to do the work.


8 men can finish half of the work in 3 days. If the remaining work is to be completed in 2 days. then the no. of additional men required are?


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×