प्रश्न
Choose the most appropriate option.
Two men and seven boys can do work in 14 days. Three men and eight boys can do the same work in 11 days. Further, eight men and six boys can do three times the amount of this work in:
विकल्प
18 days
21 days
30 days
24 days
Advertisements
उत्तर
21 days
Explanation:
According to question
(2 × 14) men + (7 × 14) boys = (3 × 11) men + (8 × 11) boys
⇒ 5 men = 10 boys or 1 man = 2 boys
∴ (2 men + 7 boys) = (2 × 2 + 7) boys = 11 boys
(8 men + 6 boys) = (8 × 2 + 6) boys = 22 boys
Let the required number of days be x
According to the ratio proportion,
Boys 22: 11 Work 1: 3] :: 14 : x
∴ (22 × 1 × x) = (11 × 3 × 14)
`∴"x"=462/22=21`
Hence, the required number of days = 21.
APPEARS IN
संबंधित प्रश्न
A tank is connected to three pipes – Pipe A, B, and C. Pipe A can fill the tank in 6 hours, B can fill the tank in 8 hours and Pipe C can empty the full tank in 12 hours. How much time will it take to fill the tank completely if all three pipes are working together?
Solve the following question and mark the best possible option.
Four gardeners with four grass mowers can mow 400 square meters of ground in four hours. How long would it take for eight gardeners with eight grass mowers to mow 800 square meters of the ground?
Twenty-five workers were employed to complete a compound wall in 12 days. Five workers left after working for 4 days. The remaining 20 workers completed the work. In how many days the total job was completed?
10 men can finish the construction of a hut in 8 days. How many men are needed to finish the same in half a day?
A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in
A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?
Two pipes P and Q can fill a tank in 15 min and 20 min, respectively. Both the pipes are opened together but after 4 min, pipe P is turned off. What is the total time required to fill the tank?
Ram can do a work in 60 days and the same work Sohan can finish in 40 days. If both of them work together, then in how many days will the work be over?
X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
B is `4/3` times as efficient as A. If A can complete `5/8`th of a given task in 15 days, what fraction of the same task would remain incomplete if B works on it independently for 10 days only?