Choose the most appropriate option.
A can do a piece of work in 8 days and B alone can do the same work in 10 days. A and B agreed to do the work together for Rs. 720. With the help of C, they finished the work in 4 days. How much C is to be paid?
विकल्प
Rs. 80
Rs. 70
Rs. 82
Rs. 72
Advertisements
उत्तर
Rs. 72
Explanation:
C's 1-day work`=1/4-(1/8+1/10)`
`=1/4-9/40⇒1/40.`
A's wages: B's wages: C's wages`=1/8: 1/10 : 1/40=5:4:1`
∴ C's share (for 4 days)`=720/10xx1=72`
= Rs. 72
APPEARS IN
संबंधित प्रश्न
Arun can climb a Coconut tree by 1.5 feet by each lift; however, he slips 0.5 feet every time he makes the next lift. How many individual lifts he will have to reach the top of the Coconut tree of 18.5 feet?
Choose the most appropriate option.
Two men and seven boys can do work in 14 days. Three men and eight boys can do the same work in 11 days. Further, eight men and six boys can do three times the amount of this work in:
10 men can finish the construction of a hut in 8 days. How many men are needed to finish the same in half a day?
A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for ₹5400. They begin the work together but B left 2 days before the completion of work and C left 5 days before the completion of work. The share of A from the assured money is
A, B, and C get ₹5400 for doing work in 36 days. A and C get ₹1880 for doing the same work in 20 days, which B and C get ₹3040 for doing the same work in 40 days. Find the amount received by C per day.
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
A fort had provision for 400 men for 60 days. After 35 days, 100 more men came. For how many days would the provisions last, assuming all men consumed food equally?
A can do a work in 6 days and B in 9 days. How many days wlll both take together to complete the work?
Working 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days?
26 men can complete a piece of work in 17 days. How many more men must be hired to complete the work in 13 days?