प्रश्न
Choose the most appropriate option.
A can do a piece of work in 8 days and B alone can do the same work in 10 days. A and B agreed to do the work together for Rs. 720. With the help of C, they finished the work in 4 days. How much C is to be paid?
पर्याय
Rs. 80
Rs. 70
Rs. 82
Rs. 72
Advertisements
उत्तर
Rs. 72
Explanation:
C's 1-day work`=1/4-(1/8+1/10)`
`=1/4-9/40⇒1/40.`
A's wages: B's wages: C's wages`=1/8: 1/10 : 1/40=5:4:1`
∴ C's share (for 4 days)`=720/10xx1=72`
= Rs. 72
APPEARS IN
संबंधित प्रश्न
16 men can do a piece of work in 16 days. 4 days after they started the work 8 more men joined them. How many days will they now take to complete the remaining work?
A can do a piece of work in 20 days and B can do the same work in 15 days. How long will they take to finish the work, if both work together?
A group of men decided to do a job in 8 days. But since 10 men dropped out every day, the job got completed at the end of the 12th day. How many men were there at the beginning?
Aarti can do a piece of work in 6 days. In how many days will she complete three times of work of the same type?
Twenty women can do a piece of work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?
A and B can together finish work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days, A alone can finish the work?
A, B, and C get ₹5400 for doing work in 36 days. A and C get ₹1880 for doing the same work in 20 days, which B and C get ₹3040 for doing the same work in 40 days. Find the amount received by C per day.
Kiran can complete a task in 15 days. He works for 5 days and then leaves. If Venkat completes the remaining task in 30 days, then in how many days can Venkat alone complete the same task?
A fort had provision for 400 men for 60 days. After 35 days, 100 more men came. For how many days would the provisions last, assuming all men consumed food equally?
Working 8 hours a day, Anu can copy a book in 18 days. How many hours a day should she work so as to finish the work in 12 days?