Choose the most appropriate option.
A can do a piece of work in 8 days and B alone can do the same work in 10 days. A and B agreed to do the work together for Rs. 720. With the help of C, they finished the work in 4 days. How much C is to be paid?
पर्याय
Rs. 80
Rs. 70
Rs. 82
Rs. 72
Advertisements
उत्तर
Rs. 72
Explanation:
C's 1-day work`=1/4-(1/8+1/10)`
`=1/4-9/40⇒1/40.`
A's wages: B's wages: C's wages`=1/8: 1/10 : 1/40=5:4:1`
∴ C's share (for 4 days)`=720/10xx1=72`
= Rs. 72
APPEARS IN
संबंधित प्रश्न
Arun can climb a Coconut tree by 1.5 feet by each lift; however, he slips 0.5 feet every time he makes the next lift. How many individual lifts he will have to reach the top of the Coconut tree of 18.5 feet?
A group of men decided to do a job in 8 days. But since 10 men dropped out every day, the job got completed at the end of the 12th day. How many men were there at the beginning?
A water tank has three taps A, B and C. A fills four buckets in 24 minutes, B fills 8 buckets in 1 hour and C fills 2 buckets in 20 minutes. If all the taps are opened together a full tank is emptied in 2 hours. If a bucket can hold 5 litres of water what is the capacity of the tank?
A does 80% of work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
A, B and C can do a piece of work in 20, 30 and 60 days, respectively. In how many days can A do the work, if he is assisted by B and C on every third day?
A, B, and C get ₹5400 for doing work in 36 days. A and C get ₹1880 for doing the same work in 20 days, which B and C get ₹3040 for doing the same work in 40 days. Find the amount received by C per day.
Two pipes P and Q can fill a tank in 15 min and 20 min, respectively. Both the pipes are opened together but after 4 min, pipe P is turned off. What is the total time required to fill the tank?
P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
A can do a work in 6 days and B in 9 days. How many days wlll both take together to complete the work?
5 men can do a piece of work in 6 days while 10 women can do it in 5 days. In how many days can 5 women and 3 men do it?