Ten men take 4 days to complete the task of tarring a road. How many days would 8 men take?

Sum
Advertisements

Solution

Number of men Number of days
10 4
8 x

More the men lesser the number of days required to finish the work. 
So, the number of men and the number of days required to complete the work are inversely proportional to each other. 

`10/8 = "x"/4`

`=> "x" = (10 xx 4)/8`

⇒ x = 5

Thus, when 8 men are involved so, 5 days will be required. 

shaalaa.com
  Is there an error in this question or solution?
Chapter 15.5: Miscellaneous Problems : Set 2 - Exercise [Page 100]

APPEARS IN

Balbharati Mathematics [English] Standard 7 Maharashtra State Board
Chapter 15.5 Miscellaneous Problems : Set 2
Exercise | Q 2 | Page 100

Video TutorialsVIEW ALL [1]

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×