Question
Ten men take 4 days to complete the task of tarring a road. How many days would 8 men take?
Advertisements
Solution
| Number of men | Number of days |
| 10 | 4 |
| 8 | x |
The more men, the fewer the number of days required to finish the work.
So, the number of men and the number of days required to complete the work are inversely proportional to each other.
`10/8 = "x"/4`
`=> "x" = (10 xx 4)/8`
⇒ x = 5
Thus, when 8 men are involved, 5 days will be required.
APPEARS IN
RELATED QUESTIONS
Complite the following table given that x varies directly as y .
| x | 6 | 8 | 10 | ... | 20 |
| y | 15 | 20 | ... | 40 | ... |
If the cost of 93 m of a certain kind of plastic sheet is Rs 1395, then what would it cost to buy 105 m of such plastic sheet?
A, B and C working together can do a piece of work in 8 hours. A alone can do it in 20 hours and B alone can do it in 24 hours. In how many hours will C alone do the same work?
If the cost of 6 cans of juice in ₹ 210, then what will be the cost of 4 cans of juice?
When the distance is kept fixed, speed and time vary directly with each other.
From the following table, determine if x and y are in direct proportion or not.
| x | 1 | 4 | 9 | 20 |
| y | 1.5 | 6 | 13.5 | 30 |
A swimming pool can be filled in 4 hours by 8 pumps of the same type. How many such pumps are required if the pool is to be filled in `2 2/3` hours?
44 cows can graze a field in 9 days. How many less/more cows will graze the same field in 12 days?
30 persons can reap a field in 17 days. How many more persons should be engaged to reap the same field in 10 days?
Here is a keyboard of a harmonium: This pattern of keys is repeated on larger keyboard. How many black keys would you expect to find on a keyboard with 14 such patterns.