Determine the optimal sequence of jobs that minimizes the total elapsed time for the data given below (processing time on machines is given in hours). Also find the total elapsed time and the idle - Mathematics and Statistics

Advertisements
Advertisements

Question

Determine the optimal sequence of jobs that minimizes the total elapsed time for the data given below (processing time on machines is given in hours). Also find the total elapsed time and the idle time for three machines.

Jobs I II III IV V VI VII
Machine A 3 8 7 4 9 8 7
Machine B 4 3 2 5 1 4 3
Machine C 6 7 5 11 5 6 12
Sum
Advertisements

Solution

Here min A = 3, min C = 5, Max B = 5. Since Min

C ≥ max B is satisfied, the problem can be converted.

into a two-machine problem.

Let Gand H be two fictitious machines

∴ G = A + B, H = B + C

The above problem can be written as:

Jobs  I II III IV V VI VII
Machine G 7 11 9 9 10 12 10
Machine H 10 10 7 16 6 10 15

Using the optimal sequence algorithm, the following sequence can be obtained.

I IV VII VI II III V

work table:

Jobs Machine A   Machine B   Machine C  
In Out In Out In Out
I 0 3 3 7 7 13
IV 3 7 7 12 13 24
VII 7 14 14 17 24 36
VI 14 22 22 26 36 42
II 22 30 30 33 42 49
III 30 37 37 39 49 54
V 37 46 46 47 54 59

∴ Total elapsed time is = 59 hrs.

Idle time for machine A = 13 hrs

Idle time for machine B = 37 hrs

Idle time for machine C = 7 hrs.