मराठी
महाराष्ट्र राज्य शिक्षण मंडळएचएससी वाणिज्य (इंग्रजी माध्यम) इयत्ता १२ वी

Determine the optimal sequence of jobs that minimizes the total elapsed time for the data given below (processing time on machines is given in hours). Also find the total elapsed time and the idle - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Determine the optimal sequence of jobs that minimizes the total elapsed time for the data given below (processing time on machines is given in hours). Also find the total elapsed time and the idle time for three machines.

Jobs I II III IV V VI VII
Machine A 3 8 7 4 9 8 7
Machine B 4 3 2 5 1 4 3
Machine C 6 7 5 11 5 6 12

Solution:

Here min A = 3, min C = 5, Max B = 5. Since Min C ≥ max B is satisfied, the problem can be converted into a two-machine problem.

Let G and H be two fictitious machines

∴ G = A + B, H = B + C

The above problem can be written as:

Jobs  I II III IV V VI VII
Machine G 7 11 9 9 10 12 10
Machine H 10 10 7 16 6 10 15

Using the optimal sequence algorithm, the following sequence can be obtained.

      VI II    

Work table:

Jobs Machine A Machine B Machine C
In Out In Out In Out
I 0 3 3 7 7 13
IV 3 7 7 12 13 24
`square` 7 14 14 17 24 36
VI 14 22 22 26 36 42
II 22 30 30 33 `square` 49
`square` 30 37 37 39 49 54
V 37 46 46 47 54 59

∴ Total elapsed time is = 59 hrs.

Idle time for machine A = `square` hrs

Idle time for machine B = `square` hrs

Idle time for machine C = 7 hrs.

रिकाम्या जागा भरा
बेरीज
Advertisements

उत्तर

Here min A = 3, min C = 5, Max B = 5. Since Min C ≥ max B is satisfied, the problem can be converted into a two-machine problem.

Let G and H be two fictitious machines

∴ G = A + B, H = B + C

The above problem can be written as:

Jobs  I II III IV V VI VII
Machine G 7 11 9 9 10 12 10
Machine H 10 10 7 16 6 10 15

Using the optimal sequence algorithm, the following sequence can be obtained.

I IV VII VI II III V

Work table:

Jobs Machine A Machine B Machine C
In Out In Out In Out
I 0 3 3 7 7 13
IV 3 7 7 12 13 24
\[\boxed{VII}\]  7 14 14 17 24 36
VI 14 22 22 26 36 42
II 22 30 30 33 \[\boxed{42}\] 49
\[\boxed{III}\] 30 37 37 39 49 54
V 37 46 46 47 54 59

∴ Total elapsed time is = 59 hrs.

Idle time for machine A = \[\boxed{13}\] hrs

Idle time for machine B = \[\boxed{37}\] hrs

Idle time for machine C = 7 hrs.

shaalaa.com
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
2025-2026 (March) Board Question Paper
Share
Notifications

Englishहिंदीमराठी


      Forgot password?