प्रश्न
Determine the optimal sequence of jobs that minimizes the total elapsed time for the data given below (processing time on machines is given in hours). Also find the total elapsed time and the idle time for three machines.
| Jobs | I | II | III | IV | V | VI | VII |
| Machine A | 3 | 8 | 7 | 4 | 9 | 8 | 7 |
| Machine B | 4 | 3 | 2 | 5 | 1 | 4 | 3 |
| Machine C | 6 | 7 | 5 | 11 | 5 | 6 | 12 |
योग
Advertisements
उत्तर
Here min A = 3, min C = 5, Max B = 5. Since Min
C ≥ max B is satisfied, the problem can be converted.
into a two-machine problem.
Let Gand H be two fictitious machines
∴ G = A + B, H = B + C
The above problem can be written as:
| Jobs | I | II | III | IV | V | VI | VII |
| Machine G | 7 | 11 | 9 | 9 | 10 | 12 | 10 |
| Machine H | 10 | 10 | 7 | 16 | 6 | 10 | 15 |
Using the optimal sequence algorithm, the following sequence can be obtained.
| I | IV | VII | VI | II | III | V |
work table:
| Jobs | Machine A | Machine B | Machine C | |||
| In | Out | In | Out | In | Out | |
| I | 0 | 3 | 3 | 7 | 7 | 13 |
| IV | 3 | 7 | 7 | 12 | 13 | 24 |
| VII | 7 | 14 | 14 | 17 | 24 | 36 |
| VI | 14 | 22 | 22 | 26 | 36 | 42 |
| II | 22 | 30 | 30 | 33 | 42 | 49 |
| III | 30 | 37 | 37 | 39 | 49 | 54 |
| V | 37 | 46 | 46 | 47 | 54 | 59 |
∴ Total elapsed time is = 59 hrs.
Idle time for machine A = 13 hrs
Idle time for machine B = 37 hrs
Idle time for machine C = 7 hrs.