18 men can reap a field in 35 days. For reaping the same field in 15 days, how many men are required?
Advertisements
Solution
Let the number of men required to reap the field in 15 days be x.
| Number of days | 35 | 15 |
| Number of men | 18 | x |
\[\text{ Since the number of days and the number of men required ro reap the field are in inverse variation, we have: } \]
\[35 \times 18 = 15 \times x\]
\[ \Rightarrow x = \frac{35 \times 18}{15}\]
\[ = 42\]
\[\text{ Thus, the required number of men is 42 } .\]
RELATED QUESTIONS
Which of the following are in inverse proportion?
The time taken for a journey and the distance travelled in a uniform speed.
Which of the following are in inverse proportion?
Area of cultivated land and the crop harvested
In which of the following table x and y vary inversely:
| x | 4 | 3 | 12 | 1 |
| y | 6 | 8 | 2 | 24 |
It x and y vary inversely, fill in the following blank:
| x | 16 | 32 | 8 | 128 |
| y | 4 | ... | ... | 0.25 |
Which of the following quantities vary inversely as other?
Journey (x km) undertaken by a car and the petrol (y litres) consumed by it.
A person has money to buy 25 cycles worth Rs 500 each. How many cycles he will be able to buy if each cycle is costing Rs 125 more?
Three persons can build a small house in 8 days. To build the same house in 6 days, how many persons are required?
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Which quantities in the previous question vary inversely with each other?
Two persons could fit new windows in house in 3 days.
How many persons would be needed to fit the windows in one day?