Draw the network for the project whose activities with their relationships are given below:

Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6
[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

Construct the network for the projects consisting of various activities and their precedence relationships are as given below:

A, B, C can start simultaneously A < F, E; B < D, C; E, D < G

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:

Activity A B C D E F G H I J K
Immediate Predecessors - - - A B B C D E H, I F, G
[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

Construct the network for the project whose activities are given below.

Activity 0 - 1 1 - 2 1 - 3 2 - 4 2 - 5 3 - 4 3 - 6 4 - 7 5 - 7 6 - 7
Duration (in week) 3 8 12 6 3 3 8 5 3 8

Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

A project schedule has the following characteristics

Activity 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 9 5 - 6 5 - 7 6 - 8 7 - 8 8 - 10 9 - 10
Time 4 1 1 1 6 5 4 8 1 2 5 7

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9
[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

A Project has the following time schedule

Activity 1 - 2 1 - 6 2 - 3 2 - 4 3 - 5 4 - 5 6 - 7 5 - 8 7 - 8
Duration (in days) 7 6 14 5 11 7 11 4 18

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

The critical path of the following network is

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

One of the conditions for the activity (i, j) to lie on the critical path is

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

In constructing the network which one of the following statements is false?

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

In a network while numbering the events which one of the following statements is false?

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

Which of the following is not correct?

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

In the context of network, which of the following is not correct

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

The objective of network analysis is to

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

Network problems have the advantage in terms of project

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

In critical path analysis, the word CPM mean

[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined

Draw a network diagram for the following activities.

Activity code A B C D E F G H I J K
Predecessor activity - A A A B C C C, D E, F G, H I, J
[10] Operations Research
पाठ: [10] Operations Research
Concept: undefined >> undefined