Draw the network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G |
| Predecessor activity | - | - | A | A | B | C | D, E |
Chapter: [10] Operations Research
Concept: undefined >> undefined
A Project has the following time schedule
| Activity | 1 - 2 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 6 | 5 - 6 |
| Duration (in days) |
6 | 8 | 4 | 9 | 2 | 7 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
Chapter: [10] Operations Research
Concept: undefined >> undefined
The following table gives the characteristics of the project
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
| Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
Chapter: [10] Operations Research
Concept: undefined >> undefined