The time (in hours) required to perform the printing and binding operations (in that order) for each book is given in the following table :
| Books | I | II | III | IV | V |
| Printing Machine M1 | 3 | 7 | 4 | 5 | 7 |
|
Binding Machine M2 |
6 | 2 | 7 | 3 | 4 |
Find the sequence that minimizes the total elapsed time (in hours) to complete the work .