For the following problem, find the sequence that minimize total elapsed time (in hours) required to complete the following jobs on two machines M1 and M2 in the order M1 - M2

Jobs A B C D E
Machine M1 5 1 9 3 10
Machine M2 2 6 7 8 4
Sum
Advertisements

Solution

The order is M1 - M2 hence required sequence is

B D C E A