For the following problem, find the sequence that minimize total elapsed time (in hours) required to complete the following jobs on two machines M1 and M2 in the order M1 - M2:
| Jobs | A | B | C | D | E |
| Machine M1 | 5 | 1 | 9 | 3 | 10 |
| Machine M2 | 2 | 6 | 7 | 8 | 4 |
योग
Advertisements
उत्तर
The order is M1 - M2 hence required sequence is
| B | D | C | E | A |