An important project at AMB consultants is running behind schedule by a month. This has upset their clients and might affect the reputation of the company in the long run. No managerial -

Advertisements
Advertisements

Question

An important project at AMB consultants is running behind schedule by a month. This has upset their clients and might affect the reputation of the company in the long run. No managerial action like assigning more workers, equipment or giving overtime has been able to solve the problem. What managerial action may now be taken by the company to avoid such a situation from arising in future?

Options

  • Revise the schedule

  • Assigning additional workers and equipment to the project

  • Get permission for further overtime work

  • Both (2) and (3)

MCQ

Solution

Revise the schedule

Explanation - 

Because no managerial effort has been successful in resolving the problem, the manager must revise the timetable to close the gap created by an improper schedule.