An important project at AMB consultants is running behind schedule by a month. This has upset their clients and might affect the reputation of the company in the long run. No managerial action like assigning more workers, equipment or giving overtime has been able to solve the problem. What managerial action may now be taken by the company to avoid such a situation from arising in future?
विकल्प
Revise the schedule
Assigning additional workers and equipment to the project
Get permission for further overtime work
Both (2) and (3)
MCQ
Advertisements
उत्तर
Revise the schedule
Explanation -
Because no managerial effort has been successful in resolving the problem, the manager must revise the timetable to close the gap created by an improper schedule.